Answer:
A. 40/100
Step-by-step explanation:
Speech is human vocal communication using language. Each language uses phonetic combinations of vowel and consonant sounds that form the sound of its words (that is, all English words sound different from all French words, even if they are the same word, e.g., "role" or "hotel"), and using those words in their semantic character as words in the lexicon of a language according to the syntactic constraints that govern lexical words' function in a sentence. In speaking, speakers perform many different intentional speech acts, e.g., informing, declaring, asking, persuading, directing, and can use enunciation, intonation, degrees of loudness, tempo, and other non-representational or paralinguistic aspects of vocalization to convey meaning. In their speech speakers also unintentionally communicate many aspects of their social position such as sex, age, place of origin (through accent), physical states (alertness and sleepiness, vigor or weakness, health or illness), psychic states (emotions or moods), physico-psychic states (sobriety or drunkenness, normal consciousness and trance states), education or experience, and the like.
Answer: 216.2 miles
Step-by-step explanation:
Alright, lets get started.
As the diagram shows, the line from point P is tangent to earth's curvature.
It means it is making right angle.
So the triangle formed will be right triangle.
Hence we can use Pythagorean theorem in it.
So from point P to center of earth, it will be hypotenuse of triangle.





taking square root, the x will be :

hence the value of x is 216.2 miles. : Answer
Hope it will help :)
Answer:
.
<_>
.
()_()
.
Step-by-step explanation:
The answer is 3 8 15 24 35
Answer:
$36.00
Step-by-step explanation:
The cost performance index (CPI) is a measure of the financial effectiveness and efficiency of a project. As a ratio it is calculated by dividing the budgeted cost of work completed, or earned value, by the actual cost of the work performed, that is to say:
CPI = Budgeted cost of work / Actual cost of work
From the statement we know that:
CPI = 1.94
Budgeted cost of work= $69.85
Cost of work in 1983 = Budgeted cost of work / CPI
Cost of work in 1983 = $69.85 / 1.94 = $36.00