Answer:
a) Process A is the bottleneck of the process
b) Hourly capacity = 60 / bottlenecktime = 60/25 = 2.4 units / hour
Explanation:
Part 1 is processed at A for 15 minutes and then at B for 10 minutes.
Thus part 1 take 15 + 10 i.e. 25 minutes two complete both processes
Part 2 is processed at C for 20 minutes.
Output from B and C i.e. part 1 and 2 respectively are fed to process D where the time taken to assemble is 15 minutes
Thus looking at the given data,
Part 1 takes longer time i.e. 25 minutes to reach process C compared to part 2 i.e. 20 minutes
So bottleneck occurs at process A and B because it takes maximum time i.e. 25 minutes
a) Process A is the bottleneck of the process
b) Hourly capacity = 60 / bottlenecktime = 60/25 = 2.4 units / hour
$4.40 per share
Explanation:
The computation of the earning per share is shown below:
Earning per share = (Net income - preference dividend) ÷ (Weighted average of number of shares)
where,
Net income is $640,000
Preference dividend is $72,000
And, the weighted average number of share is
= 120,000
Is checking account
commonly, company using checking account for a specific purpose, i.e: checking account for travel, checking account for supplies
, etc.