Answer:
The correct answer is Fire trucks.
Explanation:
According to the scenario, the given data are as follows:
1. Building blocks buy = $50
Increase in units = 100 units
2. Fire trucks buy = $20
Increase in units = 80 units
( which means in $50 Fire trucks can be bought 2.5× existing units)
So, In $50 Fire trucks increase in unit = 80 units × 2.5 = 200 units
3. Trains buy = $5
Increase in units = 15
( which means in $50 Trains can be bought 10× existing units)
So, In $50 Trains increase in unit = 15 units × 10 = 150 units
Hence, Fire trucks will give the maximum utility.
Answer:
A. about 2.0%
Explanation:
The forecasted error for week 1 is 1%. The demand for week 1 is 50 while estimated demand or forecast was 49. The difference between the two values is 1. The forecasted demand for week 2 is 50 while actual demand for week 2 is 54. The difference between the forecast and actual value is 4. The difference in week 3 is 5. Mean absolute deviation is 6% which means there can be 6% standard deviation from the forecasted values.
Answer:
the material handling cost per wall mirror is $500
Explanation:
The computation of the material handling cost per wall mirror is as follows;
= Budgeted material-handling costs ÷ material moves × moves ÷ number of wall mirrors
= $50,000 ÷ 20 × 5 ÷ 25
= $500
Hence, the material handling cost per wall mirror is $500
The same is to be considered
Answer:
Interest rates and investment
If interest rates are increased then it will tend to discourage investment because investment has a higher opportunity cost. With higher rates, it is more expensive to borrow money from a bank. Saving money in a bank gives a higher rate of return.
Answer:
the required return on the preferred stock is 3.33%
Explanation:
The computation of the required return on the preferred stock is shown below:
= Dividend ÷ Selling price per share
= $2.50 ÷ $75
= 3.33%
Hence, the required return on the preferred stock is 3.33%
We simply applied the above formula