Answer:
The correct answer is:
5.0 percent deflation between the first and second years, and 3.0 percent deflation between the second and third years. (a)
Explanation:
to calculate the percentage deflation, we will simply calculate the percentage change in price between the years stated. This is calculated as follows:
% change = 
Note that the negative sign shows a deflation.
if you use the same method for years two and three, you should get -3%, using P₁ as 142.5 and p₂ as 138.2. Hence option 'a' is correct.
Answer:
Cash payments + cash receipts = cash requirements
Explanation:
The cash budget is a budget which deals in a inflow and outflow of cash. The inflow of cash refers to the incoming of cash through receipts while the outflow of cash refers to the outgoing of cash through payments
It interprets the liquidity of the business organization whether organization has enough cash or it can be borrowed for running its organization
Therefore, the Cash payments + cash receipts = cash requirements is wrong as other equations that are given are right
Answer:
b. 0.67
Explanation:
UCL = 1 + 0.10
= 1.10 inch
LCL = 1 - 0.10
= 0.9 inch
standard deviation = 0.005 inch
mean = 1 inch
Cpk
= min[(UCL - mean)/(3*standard deviation) , (mean - LCL)/(3*standard deviation))]
= min[(1.10 - 1)/(3*0.05) , (1 - 0.9)/(3*0.05))]
= min[0.67 , 0.67]
= 0.67
Therefore, Theprocess capability index (Cpk) if the long-run process mean is 1 inch is 0.67
When the total expenses are greater than the total revenues, then the income summary account has a debit balance.
An income summary account is a temporary account in which the revenue and expenses closing entries are entered to find out the profit or loss.
In the income summary account, all the revenue account closing entries are credited, and all the expenses closing entries are on the debit side.
Thus, if the credit balance is more than the debit balance, it shows the profit and if the debit balance is more than the credit balance, it shows the loss.
Learn more about "Income summary":
brainly.com/question/9122916
Answer:
The correct total time is nineteen (19) days instead of twenty-one days.
Explanation:
Given the analysis of time for the project in parenthesis, it is feasible to merge some of the activities together by carrying them out simultaneously.
For example:
In the course of arranging and confirming the training facility to use which will last for 3 days, the development of the training material that ought to last for 5 days is brought down to a 2 days work because the initial 3 days for arrangement becomes vacant pending the reply on the final day. This brings the total days from 8 to 5.
Other days remain thus:
• Send an e-mail message to all department managers (1 day)
• Print copies of handout (2 days)
• Develop a set of PowerPoint slides (5 days)
• Conduct a practice training session with the instructor (2 days)
• Conduct the user training sessions (4 days).
Hence, total days are as follow:
5 +1 + 2 + 5 + 2 + 4 = 19 days.