Answer:
Project Scope Management is the applicable knowledge area.
Explanation:
Project Management involves the use of knowledge skills, tools, techniques to meet the requirement of the project. Other knowledge areas in Project Management include;
- Project Procurement Management
- Project Integration Management
- Project Communication Management
- Project Human Resource Management
- Project Quality Management
- Project Stakeholder Management
Project Scope Management involves explaining what the project will entail. It ensures people have a clear understanding of what the project is about.
I'm going to guess, but i would say the best answer would be B. They could file for Chapter 7 bankruptcy and discharge most of their debt.
Answer:
Required rate of return = 10.75%
Explanation:
<em>The value of a stock using the dividend valuation model, is the present value of the expected future dividends discounted at the required rate of return. The required rate of return is the cost of equity
</em>
The model is represented below:
P = D× (1+g)/ ke- g
Ke- cost of equity, g - growth rate, p - price of the stock
This model can used to work out the cost of equity, as follows:
Ke = D× (1+g)/p + g
Ke = (1.48× 1.05)/27 + 0.05
Ke= 0.107555556
Required return = 0.1075 × 100 = 10.75
Required rate of return = 10.75%
Answer: 7.67%
Explanation:
To solve this, the financial calculator will be needed
Present value = -896.87
Future Value = 1,000
N = [(25 - 5years) × 2 = 40
PMT = $45
Given the above information, we will press the financial calculator as we'll press CPT after which we then press I/Y and we'll get 5.11%
Then, the the firm's after-tax cost of debt will be:
= (5.11% x 2 )(1 - 0.25)
= (0.0511 × 2) (0.75)
= 0.07665
= 7.665%
= 7.67%
C. supplier relationship management is the answer