Answer:
To determine the current equivalent cost of a construction built in 1980 whose cost was $ 2.7 million, we must establish the relationship between the price index for that year, comparing it with that of the current year.
Taking into account that the average cost index for 1980 was 1941, and that said value is currently 3620, we can note that there was a significant increase in costs. Since 3620/1941 = 1.86, to determine the current cost of construction we must multiply its cost by 1.86.
So, since 2.7 x 1.86 = 5.022, we can establish that the equivalent cost at current prices of said building would have been $ 5,022,000.
Why estimated overhead costs (rather than actual overhead costs) are used in the costing process is explained below.
A predetermined cost is an expenditure that a company estimates ahead of time.
This cost is calculated prior to the purpose of production and includes all variable costs that affect production in a manufacturing business.
Actual overhead costs are difficult to calculate for each job, especially in a production environment with a large number of jobs.
As a result, overhead costs are allocated according to some standardized methods, which may link overhead costs to direct labor, machining time, and material used in each job.
Manufacturing overhead in a manufacturing organization refers to indirect costs that are required for production but cannot be traced back to individual products.
Machine depreciation and factory rental are two examples of manufacturing overhead costs.
Hence, computation of predetermined overhead rates is given above.
Learn more about overhead:
brainly.com/question/26082424
#SPJ4
Answer:
25%
Explanation:
Accounting rate of return =( Net income from investment ÷ Cost of investment ) × 100
Net income from investment = $100,000
Cost of investment = $400,000
Required rate of return = ($100,000 / $400,000 ) × 100
= 0.25 × 100
= 25%
Answer:
Results are below.
Explanation:
Giving the following information:
Fixed costs= $192,000
Unitary variable cost= $320 per week
Selling price per unit= $480 per week
<u>To calculate the total cost, we need to use the following formula:</u>
Total cost= fixed costs + unitary variable cost*number of units
Total cost= 192,000 + 320*number of weeks
<u>Now, the total revenue:</u>
Total revenue= selling price per week*Number of weeks
Total revenue= 480*x
<u>Finally, the break-even point in units:</u>
Break-even point in units= fixed costs/ contribution margin per unit
Break-even point in units= 192,000 / (480 - 320)
Break-even point in units= 1,200 campers
Answer:
<u>Establish project priorities</u>
Explanation:
<em>Remember</em>, we are told the project professional has been assigned to manage a project, therefore going by the guiding steps when defining a project, the next and second step he should take is to establish project priorities.
In other words, he should draft out what tasks should be done first, those for later, and so forth in other to successfully achieve/finish the project's objective.