Answer:
a. semi-autonomous
Explanation:
Semi autonomous has a dictionary meaning that states being independent to some defined extent.
In the given instance also Devon thinks that her colleagues or coworkers are somewhere between the two categories, that is up to a certain extent they are really independent in their views. While on the other hand, at some situations their views depend on the things like views of coworkers.
Thus, using the term that the coworkers are semi autonomous is correct as to the concern they can exercise their own powers in half way.
Answer:
Option B is correct.
Explanation:
In order to answer this question correctly, we first need to understand the law of demands.
Law of demands: It says that the relationship of price and quantity demanded is inversely proportional. It means if the price of a particular product goes high, then the quantity of demand will be reduced. Similarly, if the price of the product is low then the quantity of demanded will be higher.
Here,
Option B is the most relevant to the Law of Demand which says that Kathleen eats more steak when the price is low. It means when the price is low, the quantity of steak demanded is higher in Kathleen's case. Furthermore, Kathleen eats less when the price is high. It means, when the price of steak is higher then the quantity of steak demanded from Kathleen is low.
Hence, Option B is the correct option which fulfills the law of demand.
Answer:
β = 1.45
Explanation:
The beta of the portfolio is defined as an average of the betas (β) of each asset within the portfolio weighted by their respective invested amounts (A):

The beta of the portfolio is 1.45
<span>20% is the maximum speed up possible for this program.
For this problem, let's assign the time of 1 for the task when using a single processor. Now let's assume that we have an infinite number of processors available to handle the portion of the program that can be executed in parallel so that the execution time for that portion will be 0. That means that the total execution time with an infinite number of processors will be
1 * (0.80 + 0) = 1 * 0.80 = 0.80
So at best, the parallel program will take 80% of the time for the single threaded version. So the speed increase will be
(1 - 0.80) / 1 = 0.20/1 = 0.20 = 20%</span>
Answer:
$4,228,125
Explanation:
The computation of the included amount is shown below:
= Estimated production in a next year × required direct labor per hour × labor rate per hour
= 75,000 units × 4.1 hours × $13.75 per hour
= $4,228,125
We simply multiplied the estimated production with the required direct labor per hour and the labor rate per hour so that the estimated value can arrive