Answer:
Ans. A) $9,314.45
Explanation:
Hi, first we have to bring to present value the monthly payments to be made for 30 years (360 months). In order for this to be useful, we have to convert this annua compounded monthly rate (6.25%) to an effective rate, that is 6.25% / 12 = 0.5208%. Now, when we find this present value, we are going to substract it from the price of the house and that is the value of the down payment. But let´s just go ahead and do it together.
We have to use this formula to bring to present value the $1,595.85 monthly payments, for 30 years (360 months) at a rate of 6.25% (0.5208% monthly).

It should look like this


Now, let´s go ahead and find the down payment.


So, the answer is a). $9,314.45
Best of luck.
Answer:
Standard fixed overhead rate
= Budgeted fixed overhead cost
Budgeted direct labour hours
= $45,000
15,000 hours
= $3 per direct labour hour
Fixed overhead volume variance
= (Standard hours - Budgeted hours) x Standard fixed overhead rate
= (12,000 hours - 15,000 hours) x $3
= $9,000(U)
The correct answer is B
Explanation:
In this case, we need to calculate standard fixed overhead rate, which is budgeted fixed overhead cost divided by budgeted direct labour hours. Then, we will calculate fixed overhead volume variance, which is the difference between standard hours and budgeted hours multiplied by standard fixed overhead rate.
Answer:
get to work or your not getting paid. that's what I would say
Common stock is a corporate owned equity. Common stock shareholders have a right to the company's assets after all bondholders, preferred stock/shareholders and other debt holders are paid first and in full. Preferred stock has the owner entity to a fixed amount of money. Those that are preferred shareholders/stockholders receive money before any common stock holders do. They have a higher claim on assets and company earnings.
Answer: 0.8186
Explanation:
Given that;
activity To Tm Tp Te (V)^0.5 v
A 38 50 62 50 4 16
B 90 99 108 99 3 9
C 70 80 90 80 3.333333 11.11111
D 19 25 31 25 2 4
E 91 100 115 101 4 16
F 62 65 68 65 1 1
Expected duration Te = (4 × Tm + To + Tp ) / 6
Variance = ( Tp-To/6]²
variance of the critical path = 9+16 =25
SD of the critical path = ( var)^0.5 = 5
probability that the project will be completed within 210 days is given by
z = (210-200) / 5 = 2
which gives probability of 0.97725
Probability that the project will be completed within 195 days
z = (195-200) / 5 = -1
which corresponds to probability of 0.1586
Now required probability that project completes within 210 but before 195 days is given by
0.97725 - 0.1586 = 0.8186