Assuming you're talking about the US justice system . . . individuals still have rights when they are accused of criminal acts because our justice system requires that each individual be innocent until proven guilty in a court of law. Until such point that they are proven guilty, they are assumed innocent, and are entitled to the same rights as you or I am, having not committed any criminal acts. . . . THEY HAVE TO BE PROVEN GUILTY FIRST BEFORE THEY LOSE ANY RIGHTS AS A CITIZEN
Answer:
Variable cost per unit= $2.27 per machine hour
Explanation:
Giving the following information:
January 3,041 $4,032
February 3,456 $4,608
March 4,147 $6,912
April 5,184 $9,101
May 3,686 $5,760
June 5,322 $9,216
To calculate the unitary variable cost, we need to use the following formula:
Variable cost per unit= (Highest activity cost - Lowest activity cost)/ (Highest activity units - Lowest activity units)
Variable cost per unit= (9,216 - 4,032) / (5,322 - 3,041)
Variable cost per unit= $2.27 per machine hour
Answer:
Urgency / Postponement leads to customer inelastic demand of ice melt.
Explanation:
Elasticity of demand is responsive change in demand of good, due to change in price. Formula = % change in demand / % change in price
Factors Affecting Price Elasticity of Demand : Nature of commodity, Income, substitutes availability, time period, urgency / postponement, share in total expenditure,
Inelastic Demand is when demand responds proportionately less to price change. % change in demand < % change in price
Case 'Customer critically needs ice melt to drive to work' : This has inelastic demand i.e demand less respondent to price changes (he will buy that at high price too). Such because of the urgency of this demand & less scope of its postponement.
Answer:
31%
Explanation:
The current price is $3,863.99
The precious price is $5,599.99
The actual difference in price is $5,599.99 - $3,863.99
=$ 1, 736.00
Percentage decrease will be actual decrease/ original price X 100
= $ 1736.00/ $5,599.99 x 100
=0.31 x 100
=31%
Answer:
A) initial outlay = $150 million
Cash flow year 1 = [($30 - $25) x 0.6] + $25 = $28
Cash flow year 2 = [($30 - $25) x 0.6] + $25 = $28
Cash flow year 3 = [($30 - $25) x 0.6] + $25 = $28
Cash flow year 4 = [($30 - $25) x 0.6] + $25 + ($25 x 60%) + $50 = $93
B) Using a financial calculator, NPV = -$16.85 million
C) cash flow year 4 should increase by $24.667 million, meaning that the selling price must increase by $$24.667/0.6 = $41.11 million
minimum selling price $25 + $41.11 = $66.11 million