Answer:
Delayed, accelerated
Explanation:
Total or aggregate slack, is the term which is defined for the activity, is the time that this activity could delayed without impacting on the final date of the project.
It can be computed as the:
Smaller value of Late finish - Early finish field
and
Late start - Early start field
So, when project has positive total slack, few activities delayed the completion of project and when the project has negative total slack, then few activities accelerated to finish the project.
Answer:
$133,600
Explanation:
Straight line depreciation expense = (cost of asset - salvage value) / number of year
Cost of asset = $340,000 + $14,000 + $40,000 = $394,000
($394,000 - $60,000) / 5 = $66,800
The amount of accumulated depreciation at December 31, 2018 = $66,800 x 2 = $133,600
I believe the answer is false
Answer:
During the growth stage of the product life cycle, the growth of a product begins to plateau, and the company must take advantage of economies of scale and marketing messages and promotions that seek to remind customers about a great product, differentiate from competitors, and reinforce brand loyalty.
Explanation:
Hope this helped
Answer:
The correct word for the blank space is: specific job; process.
Explanation:
The cost object represents the cost of an object or department for which that cost is assigned. For instance, the repairs department of a dealership is a cost object of the repairs employees and the repair supplies. Cost objects are usually traceable thus are treated as direct costs for accounting purposes.
Then, <em>the cost object of a job order is the specific job assigned</em>; <em>while the cost object of a process costing system is the process </em>itself.