Answer: The options are given below:
A. $18.00
B. $1,036.80
C. $2.00
D. $7.20
E. $64.00
The correct option is D. $7.20
Explanation:
From the question above, we were given:
Annual demand = 100,000 units
Production = 4 hour cycle
d = 400 per day (250 days per year)
p = 4000 units per day
H = $40 per unit per year
Q = 200
We will be using the EPQ or Q formula to calculate the cost setup, thus:
Q = √(2Ds/H) . √(p/(p-d)
200=√(2x400x250s/40 . √(4000/(4000-400)
200=√5,000s . √1.11
By squaring both sides, we have:
40,000=5,550s
s=40,000/5,550
s=7.20
The creation of report with the report wizard differs from creating one with the report button because the report wizard allows the user to have more options and flexibility in the design.
<h3>What is a
report wizard?</h3>
This refers to the self-service reporting solution that enables users to create business reports quickly and efficiently.
However, the creation of report with the report wizard differs from creating one with the report button because the report wizard allows the user to have more options and flexibility in the design.
Read more about report wizard
<em>brainly.com/question/14363909</em>
#SPJ1
Answer:
C) person who works well alone
Explanation:
Answer:
The unemployment rate in Indonesia increased to 6.26 percent in the first quarter 2021 from 4.94 percent in the same quarter a year earlier, amid the economic downturn caused by the coronavirus crisis. The number of unemployed persons surged by 1.82 million to 8.75 million. Meanwhile, the number of employed declined by 2.23 million to 131.06 million, mostly in the transportation and warehouse (-0.30 percent) while that in accommodation and food services reported the largest increase (0.34 percent). Meantime, the labor force participation rate declined to 68.08 percent in the first quarter from 69.21 percent in the prior year.
Explanation:
give 5 star
Answer:
<u>A</u>
<u>Explanation</u>:
In this scenario note that it resulted to total dollar cost of the minutes provided been greater than the budgeted cost of estimated minutes.
Key word there is that the cost incurred is now above the budget, <u>therefore it is very likely that the technicians were being less competent than anticipated at their level, leading to greater cost.</u>