Answer and Explanation:
The computation is shown below:
1.
Direct Material Price Variance = Actual material cost - Actual Quantity × Standard Price
For Silver
= $13848 - 577 × 23
= $577 (U)
For Crystal
= $2926 - 7700 × 0.40
= $154 (F)
Direct Material Quantity Variance = (Actual Quantity - Standard Quantity) × Standard Price
For Silver
= (577 - 1530 × 0.40) × 23
= $805 (F)
For Crystal
= (7700 - 1530 × 5) × 0.40
= $20 (U)
2.
Direct Labor Rate Variance = Actual Cost - Actual Hours × Standard Rate
= $36915 - 3210 × 12
= $1605 (F)
And,
Direct Labor efficiency Variance = (Actual hours - Standard hours) × Standard Rate
= (3210 - 1530 × 2) × 12
= $1800 (U)
Answer:
The orrect option is A "I and III only"
Explanation:
<u>Statement (I)</u> is true as a result of to work out the speed of come is commensurate with the risks concerned as it doesn’t create any intellect to stay the Funds in portfolio.
<u>Statement (III) </u>is true as a result of it is sensible to isolate funds they need undesirable returns or an excessive amount of association with alternative investments
Answer:
A. Personal help and interaction wider.
Explanation:
Due to the physical contact and getting to physically recognise each other, the familiarity increase the level of personal relationship.
Answer:
Planned Obsolescence
Explanation:
According to my research on the answers provided, I can say that based on the information provided within the question this is most related to Planned Obsolescence. This term is basically defined exactly in the question, but in simpler terms this is a product that is specifically designed to become obsolete after a certain time frame.
I hope this answered your question. If you have any more questions feel free to ask away at Brainly.