Answer:
Explanation:
Base on the scenario been described in the question, stock variance refers to the volatility that arises from the average. Volatility shows the degree of risk that will be helpful in determining the level of risk an investor should take while purchasing a particular security.
Answer:
The correct option is E,14
Explanation:
In using the two-day moving average to forecast for the next day sales, the previous two days sales are taken , summed to up and finally averaged(that is divided by 2)
Next day forecast=sum of previous two days sales figures/number of days
sum of previous two days forecast=13+15=28
since the number of the days is 2 ,the 8 is divided by 2,28/2=14
Ultimately the next day forecast sales figure is 14 newspapers
Option A is wrong that is just considering of the two previous day, the same thing applies to option B.
Option C is the sum of previous two days sales without being divided
Answer:
Instructions are listed below
Explanation:
Giving the following information:
The high-low method involves taking the highest level of activity and the lowest level of activity and comparing the total costs at each level.
Mountain has recorded the following for the past nine months:
January:
Number of Cavities= 375
Total cost= $5,300
February:
Number of Cavities 500
TC= 5,850
March
Number of Cavities 350
TC= 5,200
April
Number of Cavities 600
TC=6,250
May
Number of Cavities 325
TC= 5,150
June
Number of Cavities 475
TC= 5,700
July
Number of Cavities 525
TC= 6,100
August
Number of Cavities 575
TC= 6,300
September
Number of Cavities 450
TC= 5,550
A) Variable cost= (Highest activity cost - lowest activity cost) / (Highest activity units - lowest activity units)
Variable cost= (6300 - 5150) / (600 - 325)= 4.18 per unit
Fixed cost= HACost - (variable cost per unit * HAUnits)= 6300 - (4.18*600)= 3792
Fixed cost= LACost - (variable cost per unit* LAUnits)= 5150 - (4.18*325)= 3792
B) Q= 400
Total cost= 3792 + 4.18*400= $5464
Answer:
$50? ($150 is not the correct answer)
Explanation:
Answer:
$200,000
Explanation:
Interest calculation is based on the Principle amount of $2,500,000 borrowed .