Answer:
Project Management Office is the correct answer.
Explanation:
Project Management Office is a department that focuses on and maintains the quality and overview of project management throughout the organization.
The objective of the Project Management Office is to give a platform that supports all the project teams to achieve and improve the chances of successful outcomes.
 
        
             
        
        
        
You would get 20 basketballs at $30 and 30 basketballs at $20.
        
             
        
        
        
Answer:
The budgeted materials needed in units for April is 64,800 units
Explanation:
In order to calculate the budgeted materials needed in units for April we would have to use the following formula:
Budgeted Materials =Materials needed +ending inventory −beginning inventory available
To calculate the ending inventory we would have to use the following formula:
Ending inventory=0.3×Following month budgeted materials
Ending inventory=0.3×62,000
Ending inventory=18,600
Therefore, Budgeted Materials =66,000+18,600−19,800
Budgeted Materials= 64,800 units
The budgeted materials needed in units for April is 64,800 units
	
 
        
             
        
        
        
<span>This best reflects the broader regulatory environment in which the firm operates. Changes in this environment will undoubtedly have effects on the firms future product offerings and bottom line.</span>