Answer:
the standard deviation of the critical path is 8
Step-by-step explanation:
The computation of the standard deviation of the critical path is shown below:
As we know that
Variance = Standard deviation^2
Now the variance of the critical path is
= Variance 1 + variance 2 + variance 3 + variance 4
= 4^2 + 4^2 + 4^2 + 4^2
= 64
Now the standard deviation would be
= √64
= 8
hence, the standard deviation of the critical path is 8