1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
ollegr [7]
3 years ago
7

Your project to obtain charitable donations is now 30 days into a planned 40-day project. The project is divided into 3 activiti

es. The first activity is designed to solicit individual donations. It is scheduled to run the first 25 days of the project and to bring in $25,000. Even though we are 30 days into the project, we still see that we have only 90 percent of this activity complete. The second activity relates to company donations and is scheduled to run for 30 days starting on day 5 and extending through day 35. We estimate that even though we should have approximately 83 percent (or more precisely 25/30) of this activity complete, it is actually only 50 percent complete. This part of the project was scheduled to bring in $150,000 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $50,000. So far $175,000 has actually been brought in on the project. Calculate the schedule variance, schedule performance index, cost (actually value in this case) variance, and cost performance index. (Negative values should be indicated by a minus sign. Do not round your intermediate calculations or "variance" values. Round your "performance index" values to 3 decimal places.) Schedule variance $ Schedule performance index Cost variance $ Cost performance index
Business
1 answer:
Shtirlitz [24]3 years ago
6 0

Solution:

The discretionary revenues of the work week must be estimated first before the 30th day of each operation

BRWS _{A}= Budgeted revenues * plan completion till the date

=25,000 *100%

=$ 25000

BRWS _{A} = Budgeted revenues * plan completion till the date

=150,000 *83.33%

=$ 125000

BRWS _{C} = Budgeted revenues * plan completion till the date

=50,000 *0%

=$ 0

BRWs of the project

=25000+12500+0

=150,000

The budgetary revenue from the work carried out is measured now before the 30th day of every operation.

BRWPA = Budgeted revenues * Actual completion till the date

=25,000 *90%

=$ 22500

BRWPB = Budgeted revenues * Actual completion till the date

=150,000 *50%

=$ 75000

BRWPC = Budgeted revenues * Actual completion till the date

=50,000 *0%

=$ 0

BRWP of the project

=22500+7500  

=97500

Now we need to calculate the schedule variance as under  

= BRWP-BRWS

=97500-150,000

=-52500

The deviation is so pessimistic here so that we can assume that the project's success is way behind the cost efficiency index estimate.

Calculation of the scot's expense efficiency index

=Budgeted Revenue of the work Performed / Actual revenue

=97500 /175,000

=0.56

Here, the performance level is lower than 1 (0.56) so the results are higher than expected Estimation of the performance index of the schedule

=Budgeted Revenue of the work Performed / budgeted revenue of the work scheduled

=97500 /150,000

=0.65

Here it is less than 1 (0.65) so it is behind the schedule

You might be interested in
Which of the following will typically offer the highest interest rate
max2010maxim [7]

Answer:

savings bond

Explanation:

5 0
3 years ago
Read 2 more answers
Impala is currently producing 100 units of a necessary component part by incurring $42,000 in direct materials, $8,750 in direct
photoshop1234 [79]

Answer:

If Impala decides to buy from the external source , it would then save the fixed of $1,750

Decision: Impala should be buy from the external source

Explanation:

<em>To determine the appropriate course of action, we shall determine whether there would be a net savings in cash flow as a result of purchasing externally or not.</em>

The relevant cash flows figures include:

  1. Internal variable cost of production
  2. External purchase price
  3. Savings in internal; fixed cost as result of buying outside

Variable cost of internal production = 42,000 + 8,750 + 15,750 = 66,500

Increase in variable cost if purchased externally = 66500 - 66500 = 0

If Impala decides to buy from the external source , it would then save the fixed of $1,750

Decision: Impala should be buy from the external source

6 0
3 years ago
Santana Industries purchased a supply of electronic components from ABC Corporation on October 1, 2020. In payment for the $5 mi
pshichka [43]

Answer: they will report an interest expense of $150000 in December 2020

Explanation:

firstly we calculate how much interest will be accumulated for the whole year so we are given a $5 million Dollar purchase which is the amount that will accumulate interest over time, then we have been told the company ha issued a 1 year installment note therefore we have a time frame.

so now we will calculate the yearly interest of $5 million :

$5 000000x12% = $600000 so the company will accumulate this interest yearly then we divide this amount by 12 to get the monthly interest.

$600000/12 = $ 50000 per month interest thereafter we will multiply the monthly interest of $50000 by 3 months which is months from October to December.

therefore the interest expense to be reported on the December 2020 income statement is $50000 x 3= $150000

6 0
3 years ago
Net present value: Select one: is the best method of analyzing mutually exclusive projects. is less useful than the internal rat
Leto [7]

Answer:

Is the best method of analyzing mutually exclusive projects.

Explanation:

Net present value is equal to the present value of all the future cash flows of a project, less the initial outlay of project.

Net present value analysis simply concluded about a project to be worth doing when it finds the present value of future cash flows greater than the initial investment and vice versa.

We just have to see which is higher, the present value of future cash flows or the initial investment.

It is assumed that an investment with a positive NPV will be profitable, and an investment with a negative NPV will result in a net loss.

3 0
3 years ago
g You currently hold an inflation-indexed bond, which pays out real coupons of 10% per year, starting one year from now. The bon
Allushta [10]

Answer:

$618 dollars

Explanation:

The beginning face value will be our starting position: $600

Then, we have a 2 percent increase over the next three years

this makes for a principal at maturity of:

600 x (1 + 2% x 3 years ) = $618

This makes each coupon return in coins to also increase over time as, they are calcualted based on the adjusted face vale. This method iguarantee the 10% return on the bond regardless of inflation during the period.

3 0
3 years ago
Other questions:
  • Suppose a museum charges different entrance fees for children, students, adults and seniors, but these groups all pay the same a
    5·1 answer
  • 1. How to interview for success <br> 2. Understanding the interview proccess
    14·1 answer
  • Which one of the following statements is TRUE? a. Company sponsorship of a local charity is an example of a nonpecuniary benefit
    11·1 answer
  • Cost of goods sold is obtained from _________.
    11·2 answers
  • If JJ Camera had a policy that says no Muslim employees are allowed to work on the sales floor, the policy would be an example o
    11·1 answer
  • After the accounts are adjusted and closed at the end of the fiscal year, Accounts Receivable has a balance of $703,938 and Allo
    5·1 answer
  • Which response might be an answer to a fundamental question of economics of who should produce? A. The cost of a car will be abo
    14·1 answer
  • Grocery stores frequently put new products in high visibility locations such as the end of an aisle or near the checkout lanes.
    6·1 answer
  • You invest $200 in stocks and sell them one year later for $230. Use the instructions in Lesson 3 to calculate the ROI dollar am
    13·1 answer
  • In Macroland there is $10,000,000 in currency. The public holds half of the currency and banks hold the rest as reserves. If ban
    6·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!