Answer:
Explanation:
Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?
Since B is the predecessor of C.
Project completion time for each run will be calculated as Maximum (Duration of A, Duration of B +Duration of C).
Represent
Run = R
Duration of A = DA
Duration of B = DB
Duration of C = DC
Project Completion time = PT
<u>R DA DB DC PT</u>
1 51 48 17 48 + 17 = 65
2 60 48 19 48 + 19 = 67
4 31 48 22 48 + 22 = 70
5 30 31 14 31 + 14 = 45
6 41 16 17 41
7 44 12 6 44
8 44 12 10 44
9 45 43 9 43 + 9 = 52
10 60 41 10 60
<u> Total = 546</u>
Total Project completion time in 10 Stimulations = 546
Average project Completion time = 546/10 = 54.6
Therefore, average Project completion time is between 53 and 56 days.
Two taxes on employers, two taxes on employees, OASDI and HI taxes and taxes on the net earnings of the self-employed
<span>Compared with many European countries the party in government system in the united states is less differentiated. (have a lesser amount)
In many European countries, the parties that involved within the government could account to more than 4 parties. Meanwhile, there are only 2 major political parties in the United States, Democratic party and the republican party</span>
Answer:money income
Explanation: I think it’s money income not for sure though