Answer:
he is incorrect.
Step-by-step explanation:
It would be 5 and 38 HUNDRETHS because the first number after the decimal is the tenths.
Answer:
15.06
Step-by-step explanation:
I don't have a step-by-step explanation, but i hope this helps!!!
Answer:
d. 20
Step-by-step explanation:
To answer the question given, we will follow the steps below:
we need to first find p(3)
p(x) = x+ 7/ x-1
we will replace all x by 3 in the equation above
p(3) = 3+7 / 3-1
p(3) = 10/2
p(3) = 5
Similarly to find q(2)
q (x) = x^2 + x - 2,
we will replace x by 2 in the equation above
q (2) = 2^2 + 2 - 2
q (2) = 4 + 0
q (2) = 4
The product of p(3) and q(2) = 5 × 4 = 20
Answer:
the third one
Step-by-step explanation:
Answer:
required probability is .3446
Step-by-step explanation:
It is given that most expected time of completion = 90 days
Variance = 25
We know that

Thus the standard normal deviate is given by

Applying values we get

Using the standard table for Z we have probability corresponding to Z = -0.4 equals 0.3446
Thus required probability is .3446