Answer:
d. It determines the critical path for the completion of a series of interrelated activities.
Explanation:
The Critical Path method is a method to lay out the different steps or interrelated activities of a project, in a graphical manner, that shows the interrelations, the time each activity takes to complete, the different alternatives or paths for project completion, and the total completion time for the project.
It also shows the amount of time a delay in one of the activities would delay the project as a whole.
Answer:
Its action would be optimal given an ordering cost of $28.31 per order
Explanation:
According to the given data we have the following:
economic order quantity, EOQ= 55 units
annual demand, D=235
holding cost per one unit per year, H=40%×$11=$4.4
ordering cost, S=?
In order to calculate the ordering cost we would have to use the following formula:
EOQ=√(<u>2×D×S)</u>
(H)
Hence, S=<u>(EOQ)∧2×H</u>
2×D
S=<u>(55)∧2×4.4</u>
2×235
S=<u>13,310</u>
470
S=$28.31
Its action would be optimal given an ordering cost of $28.31 per order
Answer: b. 233,500
Explanation:
The expected cashflow is;
= (EBIT * (1 - tax) ) + Depreciation - change in net working capital - capital expenditure
= (270,000 * (1 - 25%)) + 85,000 - 19,000 - 35,000
= $233,500