1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
olasank [31]
3 years ago
14

The problem now is to decide which contractor to choose.B has indicated that for another $20 million he could do the job in 18 m

onths, and you have said that you would be indifferent between that and the original proposal. In talking with C, you have indicated that you would just as soon pay her an extra $4 million if she could get the job done in 26 months. Who gets the job?

Business
1 answer:
Ede4ka [16]3 years ago
8 0

Question: The question is incomplete. See the full question below and the answer.

You are an up-and-coming developer in downtown Seattle and are interested in constructing a building on a site you own. You have collected four bids from prospective contractors. The bids include both a cost ($millions) and time to completion (months):

Contractor    Cost           Time

A                   100             20

B                    80              25

C                    79               28

D                   82                26

The problem now is to decide which contractor to choose. B has indicated that for another $20 million, he could do the job in 18 months, and you have said that you would be indifferent between that bid and the original proposal. In talking with C, you have indicated that you would just as soon pay her an extra $million if she could get the job done in 26 months. Who gets the job? Explain your reasoning. (It may be convenient to plot the four alternatives on a graph.)

Answer:

See the explanation for the answer and find attached of the graph.

Explanation:

So we draw a regression line of Time vs Cost and best fit a curve based on the data given, given in the above figure. The four alternatives are marked in the figure as well. Our main objective is to reduce both time and cost, but that might not be possible So the best thing would be to look for alternatives which lie below the line. If C gets an extra million, then that point would come below the regression line, and it would be a better alternative than D, because for the same time we are getting the job done at a cheaper cost.

Also if B is paid extra 20 million, that point also comes below the regression line, and hence will be a better alternative than A because for the same cost again we are getting the job done earlier. We need to choose between B and C. Now in order to optimise both cost and time, we need to choose a point close to the middle point of the regression line segment in 1st quadrant. We see that C is much more closer to the middle point and hence seems like a better option.

So we choose C as our contractor if we consider B's alternative bid, but if we do not consider B's alternative bid and stick to the original one, we choose B as our contractor.

You might be interested in
The government can make money by borrowing from its population in the form of governmental bonds.
sladkih [1.3K]
False I think I’m not sure tho
8 0
3 years ago
Read 2 more answers
Productive inefficiency could arise from a. a waste of available labor b. a lack of resources c. an improvement in technology d.
kolezko [41]

Answer:

The correct answer is a. a waste of available labor.

Explanation:

Productive efficiency (also known as technical efficiency) occurs when the economy is using all its resources efficiently, producing maximum production with minimum resources. The concept is illustrated in the Production Opportunity Frontier (FPP) in which all points of the curve are the points of maximum productive efficiency (that is, no more products can be achieved from the present resources).

This happens when the production of an economic good is achieved at the lowest possible cost, given the production of another good (s). In other words, when it is achieved, given the need to produce other goods, the highest possible productivity of a good. In a situation of long-term equilibrium for markets in perfect competition, it is where the average cost is the base on the average of the total cost curve, that is, the cost curve where CM = A (T) C.

6 0
4 years ago
Stoltenberg Co. had the following information for the month of June: Work in process beginning inventory, June 12,300units Units
solniwko [45]

Answer:

the number of units started and completed in June is 24,900 units

Explanation:

The computation of the number of units started and completed in June is shown below;

= Opening work in process inventory + transferred units - ending work in process units

= 12,300 units + 16,900 units - 4,300 units

= 24,900 units

hence, the  number of units started and completed in June is 24,900 units

4 0
3 years ago
Which country has had a higher growth rate than the US over about the last 120 years?
Drupady [299]
Highest growth rate based on GDP rate is found in Japan. This has been an ongoing trend for the last 100 years.
6 0
3 years ago
The bank loan of $2,000,000 requires Irkalla to maintain certain financial ratios but Irkalla has not been able to do so and is
aalyn [17]

Answer:

Current liabilities at December 31, 2014 for Irkalla;

$200,000 + $100,000 + $2,000,000 + $1,000,000 = $3,300,000.  

Method of reasoning: Accounts payable-exchange and Short-term borrowings consistently fall under "Current Liabilities". Development for Other bank advance has not explicitly given (for example develops June 30, 20 × 5), so we accept it to develop on June 30, 2015. Since development is expected inside 1 year, it additionally falls under current risk as term is just a single year. On the bank credit of $2,000,000, Irkella has damaged the terms, so now this advance is likewise required to be paid off soon and thus it additionally now goes under "Current Liabilities"

8 0
4 years ago
Read 2 more answers
Other questions:
  • Beth Caldwell is in the payroll accounting department of Acerill Films. An independent contractor of the company requests that S
    7·1 answer
  • If a firm sold $700 worth of goods that cost $800 to produce:
    12·1 answer
  • Redbox places vending machines at local convenience and grocery stores that allow customers to rent and return popular DVDs 24 h
    7·1 answer
  • At the beginning of the year, the balance in Allowance for Doubtful Accounts is a credit of $760. During the year, previously wr
    13·1 answer
  • A growling sound is heard from the rear of a rear-wheel-drive vehicle during cornering only. Technician A says that defective re
    14·1 answer
  • On April 1, 2020, Tamarisk Company received a condemnation award of $447,200 cash as compensation for the forced sale of the com
    13·1 answer
  • By addressing customer complaints as quickly as possible, even in the middle of a model year, is demonstrating ____.
    7·1 answer
  • The total factory overhead for Bardot Marine Company is budgeted for the year at $1,010,625, divided into two departments: Fabri
    6·1 answer
  • A major beverage company faced criticism of various groups and parents for contributing to childhood obesity by selling its suga
    11·1 answer
  • Which of the following is an internet job search "do"
    10·2 answers
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!