Answer:
following are the OSI Layers
1.physical layer
2.datalink layer
3.network layer
4.transport layer
5.session layer
6.presentation layer
7.application layer
Explanation:
physical layer is used to transmit media,signal and binary information
datalink layer is used for physical addressing MAC and LLC
network layer is used for path determination and ip
transport layer is for end to end communication and reliability
session layer is for interhost communication
presentation layer is for data representation and encryption
application layer is network process to application
Answer:
Keep Source Formatting & Embed Workbook
Explanation:
Source formatting is used to apply the formatting from source document while copying and pasting.
Source is the place where the data is already placed and we want to move it make a copy of it on some other document. So if we don't want to change the formatting of source document, we choose source formatting from the options while pasting.
Embed is used to whenever we don't want to link the formatting with source document.
So,
You use the Paste Options button labeled <u><em>Keep Source Formatting & Embed Workbook</em></u><em> </em>if you want the pasted chart not to be linked to the source document and you want the pasted chart to keep the formatting from the source document.
Answer:
B. Click the Next icon on the Reviewing toolbar to review and then accept or reject each edit.
Explanation:
Since Jack wants to keep some changes and reject others, he can't use a global solution (like presented in answers A and C).
He has to go through each and every change proposition and decide individually if he wants to keep the change or not. That's why it's answer B.
It's the only way to accept some, reject some.
At the end of this process, he'll have a clean document with Rob's recommendations and his original documents.
Answer:
There are multiple critical paths
Explanation:
The critical path method (CPM), or critical path analysis (CPA), is an algorithm for scheduling a set of project activities. It is commonly used in conjunction with the program evaluation and review technique (PERT). A critical path is determined by identifying the longest stretch of dependent activities and measuring the time required to complete them from start to finish.
The essential technique for using CPM is to construct a model of the project that includes the following:
- A list of all activities required to complete the project (typically categorized within a work breakdown structure),
- The time (duration) that each activity will take to complete,
- The dependencies between the activities and,
- Logical end points such as milestones or deliverable items.
Using these values, CPM calculates the longest path of planned activities to logical end points or to the end of the project, and the earliest and latest that each activity can start and finish without making the project longer. This process determines which activities are "critical" (i.e., on the longest path) and which have "total float" (i.e., can be delayed without making the project longer).
considering the above function of the cpm analysis because you have multiple path, there is tendency that more than path through the project network will have zero slack values.
Answer:
change how big or small the shape or sprite is