In project management, earliest finish time for activity A refers to the earliest start time for succeeding activities such as B and C to start.
Assume that activities A and B comes before C, the earliest finish time for C can be arrived at by computing the earliest start-finish (critical path) of the activity with the largest EF.
That is, if two activities (A and B) come before activity C, one can estimate how long it's going to take to complete activity C if ones knows how long activity B will take (being the activity with the largest earliest finish time).
Cheers!
Answer:
A. CSR
Explanation:
CSR, (certificate signing request also known as certification request, CR) are messages sent by an applicant to a certificate authority to acquire a digital identification certificate or renew an already existing one. It contains information of the client or applicant like domain name, public key etc.
Keyescrow, CRLD and OCSP are not recommended or required for renewing digital certificate as they commands or settings for shortcuts and commands.