There are different kinds of software implementation strategy. The software implementation strategy would you recommend in this situation to allow users fall-back access to the old system as the new one is implemented is parallel start up.
- Parallel running often called parallel start up strategy for system changeover where a new system slowly takes over the roles of the older system even when both systems operate.
This conversion often occur when the technology of the old system is outdated and as such a new system is needed to be installed to replace the old one.
The parallel running phase is the act of changing a fragment of business information technology operation to a new system.
Learn more about Parallel start up from
brainly.com/question/9343211
The answer is Class A. The GFCI (Ground Fault Circuit Interrupter) will “sense” the difference in the
amount of electricity flowing into the circuit to that flowing out, even in
amounts of current as small as 4 or 5 milliamps. The GFCI reacts
quickly (less than one-tenth of a second) to trip or shut off the circuit.
I guess the word in the blank is Standardization.
Human systems integration (HSI), a supportability issue that every program should consider, addresses such factors as accessibility, visibility, testability, and Standardization.
The pseudocode to find the sum of all integers that are multiples of 9, from 1 to 250.
totalSum = 0
for i from 1 to 250{
if i is divided by 9 and remainder is 0{
totalSum = totalSum + i;
}
}
print(totalSum)
in python language the code will be
totalSum = 0
for i in range(1,250):
if i%9==0:
totalSum += i
If you will run the program , the answer would be 3402.
Answer:
The answer is "Option d".
Explanation:
The Iteration Management is also an activity in which all members of the team will determine how many the backlog team will allocate towards the next Iteration, and each team wraps up the work only as a group of determined iteration targets. in the given question the "choice d" is correct because The plans to achieve without training entered PO or design staff and requirements have not even been identified, and the wrong choice can be defined as follows:
- In choice A, T' he PO doesn't give the story detail, that's why it's incorrect.
- In choice B, the doesn't a team left the past for more refining with the PO in the Project Backlog, that's why it's incorrect.
- In choice C, The Development Team has not found some other team dependency, that's why it's incorrect.