Answer:
<h2><u>
36x
/y
</u></h2>
Step-by-step explanation:
Hope this helps
<h2><em>
:)</em></h2>
Answer:
Fourth option: 30 days
Step-by-step explanation:
We three path to complete the project:
Path A:
A1 → A2 → A3
10 days → 8 days → 9 days = 27 days
Path B:
B1 → B2 → B3
2 days → 7 days → 3 days = 12 days
Path C:
C1 → C2 → C3
10 days → 8 days → 12 days = 30 days
Then the duration of the critical path is 30 days, we can't conclude the project until each path has finished
The whole number is 10 the square root is 9
Por determinante:
5...1...1
1...0...1 = 0 --> se o determinante for igual a 0, os pontos estarão alinhados.
3...3...1
calculando: (5 x 0 x 1 + 1 x 1 x 3 + 1 x 3 x 1) - (1 x 0 x 3 + 1 x 1 x 1 + 3 x 1 x 5) =
0 + 3 + 3 - 0 - 1 - 15 =
6 - 1 - 15 =
5 - 15 = - 10 --> como não deu zero, os pontos não estão alinhados.