The LCM (least common denominator) of 3, 4, 6 and 8 is...
24
Answer:
the first one
Step-by-step explanation:
A graph showing the Earliest Start Times (EST) for project tasks is computed left to right based on the predecessor task durations. For dependent tasks, the earliest start time will be the latest of the finish times of predecessor tasks.
The first graph appears to appropriately represent the table values, using edges to represent task duration, and bubble numbers to represent start times.
The second graph does not appropriately account for duration of predecessor tasks.
The third graph seems to incorrectly compute task completion times (even if you assume that the edge/bubble number swap is acceptable).
To solve this you can use subtraction
186-27=159 (for the amount Eric gave away)
So Eric has 159 stars left!
Hope this helped!!
One way to do it is you can draw two sets of 7/8.
You can draw 8 tiles, and color in 7.
Draw that two times.
That’s one way, but that might not be the way you learned it.
Hope this helped anyways!
Answer:
Law of Syllogism
Step-by-step explanation: