1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
Nataly [62]
3 years ago
15

A prism has a total surface area of 228 m2 and volume of 216 m3.

Mathematics
1 answer:
telo118 [61]3 years ago
4 0
Multiply by 1/3 to reduce.
228*1/3=76m^2
216*1/3=72m^3

Multiply by 4 to increase.
228*4=912m^2
216*4=864m^3

I can explain more if you need.
You might be interested in
-12-x&gt;-12+4x<br> put the steps too pls thanks
andrey2020 [161]

Answer:

x < 0

Step-by-step explanation:

Firstly put the values with variable x to one side,

; -12 - x > -12 + 4x

; -12 + 12 > 4x + x

; 0 > 5x

then divide both sides by 5,

; (0 ÷ 5) > (5x ÷ 5)

; 0 > x

; Hence the solution to the inequality above,

; x < 0...always remember to reverse the sign when you change the side to which you put the variable of x,

Therefore...( x < 0 )

3 0
3 years ago
The following histogram shows the number of items sold at a grocery store at various prices:
monitta

Answer:

<h2><u><em>its B</em></u></h2>

Step-by-step explanation:

8 0
3 years ago
Read 2 more answers
Which of the following is NOT a reason fitness testing is useful in schools?
EastWind [94]
The most relevant answer is B
6 0
2 years ago
Joe used a project management software package and has determined the following results for a given project.: Expected completio
statuscvo [17]

Answer:

0.1151 = 11.51% probability of completing the project over 20 days.

Step-by-step explanation:

Normal Probability Distribution

Problems of normal distributions can be solved using the z-score formula.

In a set with mean \mu and standard deviation \sigma, the z-score of a measure X is given by:

Z = \frac{X - \mu}{\sigma}

The Z-score measures how many standard deviations the measure is from the mean. After finding the Z-score, we look at the z-score table and find the p-value associated with this z-score. This p-value is the probability that the value of the measure is smaller than X, that is, the percentile of X. Subtracting 1 by the p-value, we get the probability that the value of the measure is greater than X.

Expected completion time of the project = 22 days.

Variance of project completion time = 2.77

This means that \mu = 22, \sigma = \sqrt{2.77}

What is the probability of completing the project over 20 days?

This is the p-value of Z when X = 20, so:

Z = \frac{X - \mu}{\sigma}

Z = \frac{20 - 22}{\sqrt{2.77}}

Z = -1.2

Z = -1.2 has a p-value of 0.1151.

0.1151 = 11.51% probability of completing the project over 20 days.

4 0
2 years ago
Please help me asap !!!
Georgia [21]

Answer:

y=5x+7

Step-by-step explanation:

8 0
2 years ago
Other questions:
  • I need to solve the whole thing
    9·1 answer
  • What algebraic expression models the word phrase three fewer than the sum of c and d?
    15·2 answers
  • The base of a pyramid has n sides. write an expression for the number of corners on the pyramid.
    5·1 answer
  • How does having a different strategy to try when you encounter a roadblock help?
    10·1 answer
  • charlotte has invited 75 people to her party. The buffet menu below if for 25 people. Work out how many of the following she wil
    7·2 answers
  • Find the equation of the line with the given slope that passes through the given point. Write the
    5·1 answer
  • What is the area of the square given the side length 20.5in
    12·2 answers
  • 3 800 millimeters expressed in metres is​
    7·2 answers
  • What is 2/9 + (-1/2) simplified?
    14·2 answers
  • Bobby is buying ribs for his 4th of July cookout. The ribs are on sale for $3.50 per pound. If Bobby buys 5.5 pounds of ribs, ho
    12·2 answers
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!