Answer:
Find attached statement and the question which question number 10.
The correct option is C,$90
Explanation:
In the statement you would notice that the balance transfer from another credit card was $785,upon which balance transfer levy of $23.55 was charged(Section 7)
Intuitively, the percentage of balance transfer charge is $23.55 divided by the amount of balance transfer i.e $785
balance transfer charge(%)=$23.55/$785=3%
However, if the balance transfer were $3000,the charge is 3% of $3000 i.e $90 ($3000*3%).
The correct option then is C,$90
Answer: If the required return is 11 percent, what is the project's NPV? (Do not round intermediate calculations and round your answer to two decimal places, e.g., 32.16.)
Explanation:
Answer:
useful
Explanation:
i got it from USA test prep
The variable overhead efficiency variance uses exactly same inputs as direct labor efficiency variance statement regarding the variable overhead variance analysis is true.
<h3>
What is variable overhead?</h3>
The varying production costs a business incurs while operating are referred to as "variable overhead." As industrial output changes, so do variable overhead expenses. Different from variable overhead are the general expenditures associated with administrative tasks and other operations that have predetermined budgetary requirements. Organizations need to understand variable costs clearly in order to prevent overspending, which can reduce profit margins. They will be able to precisely set prices for future products thanks to this. For businesses to succeed and stay in operation, they must invest money in the development and promotion of their goods and services. The term "overhead" refers to all costs related to operating a firm, such as managers, salespeople, and marketers for both the corporate office and the manufacturing plants.
To learn more about variable overhead, visit:
brainly.com/question/27993032
#SPJ4
Answer:
Option (D) is correct.
Explanation:
Total Overhead Cost:
= (Overhead × Number of cases) for all products
= (20 × 350) + (25 × 550) + (17 × 650)
= 31,800
Total Machine Hours:
= Machine hours × Number of cases
= (5 × 350) + (3 × 550) + (4 × 650)
= 6,000
Overhead Rate:
= Total Overhead Cost ÷ Total Machine Hours
= 31,800 ÷ 6,000
= 5.30
Total product cost per case for Product GC:
= Direct Material + Direct Labor + Overhead
= 80 + 30 + (Machine hours × Overhead Rate)
= 80 + 30 + (3 × 5.3)
= 80.00 + 30.00 + 15.90
= $125.90