Answer: The probability that the project will be completed in 33 days or less is equal to<u> </u><u>0.73</u> .
Step-by-step explanation:
We assume that this is a normally distribution.
Given : The critical path length is 30 days .
i.e. Population mean = 
Variance : 
Then, standard deviation : 
Z-score : 
The value of z corresponding to 33 = 
Now, the p-value = 
Hence, the probability that the project will be completed in 33 days or less is equal to 0.73.
Answer:
I just need points to ask my own question sorry
Answer:
She had 38!
Step-by-step explanation:
28-9 is 19 then just multiply that by two which is 38
Answer:
Rational
Step-by-step explanation:
Rational number consists of
- Whole Numbers
- Natural Numbers
- Integers
- Negative Numbers
- Fractions
- Decimals
-5/6 is a Fraction and we can also simply it to a Decimal.
Hope this helps ;) ❤❤❤
Answer:
557.89
Step-by-step explanation:
Download photomath on Appstore it'll help you explain. but basically you multiply each digit at the bottom to the whole number on the top
23.50
<u>x </u><u>23.74</u>
940 ====== 23.50 multiply to 4
16450 ====== 23.50 multiply to 7
70500 ====== 23.50 multiply to 3
<u>+ 470000 </u> ====== 23.50 multiply to 2
557.890 ====== Add all the numbers together, move the decimal sign down to align with the result
<u />