Total work amount
6 men * 14 days
84 men days
If it is done within 21 days, need x men
84 men days = x men * 21 days
x = 84/21 men
x = 4 men
3 + 5(c + 3) = -17
First, subtract 3 from both sides. / Your problem should look like:
Second, simplify -17 - 3 to get -20. / Your problem should look like:
Third, divide both sides by 5. / Your problem should look like:
Fourth, simplify

to 4. / Your problem should look like:
Fifth, subtract 3 from both sides. / Your problem should look like:
Sixth, simplify -4 - 3 to get -7. / Your problem should look like:

Answer:
c = -7
Answer:
Step-by-step explanation:
arranging in ascending order
45,57,70,72,78
number of terms=5
median=(5+1)/2=3rd
or median =70
Answer:
$5,675
Step-by-step explanation:
you would just take 4% and 5% of 2500 which is 100 and 125 and multiply them both by 3 which is 300 and 375 and add them both to the 2500 which is 2800 and 2875 and since it asks for the sum you would add then to get a total of $5,675