Question Completion:
Epsilon Co. can produce a unit of product for the following:
Direct material $8
Direct labor 24
Overhead 40
Total costs per unit $72
Answer:
Epsilon Co.
Epsilon should choose to:
Make since the relevant cost to make it is $56.
Explanation:
a) Data and Calculations:
Direct material $8
Direct labor 24
Overhead 40
Total costs per unit $72
Relevant Costs:
Make Buy
Direct material $8
Direct labor 24
Overhead 24
Total costs per unit $56 $60
b) It costs Epsilon less to make the units than to buy from the outside supplier. The relevant cost excludes the 40% of the overhead that will still be incurred by Epsilon if it buys from the supplier. Relevantly, it costs Epsilon $56 per unit to make when compared to the unit cost of $60 to buy. In absolute terms, it will cost Epsilon $76 ($60 + $16) to buy as against $72 to make a unit of the part.
Answer:
Variety diversity
Explanation:
It is correct to state that the form of diversity found in the example above is the diversity of variety, which corresponds to the inclusion of people of different cultures, genders, races, ages, etc., in a workplace.
This diversity can be very positive and add a lot to the efficiency of the team, which with a greater variety of functional backgrounds and work experiences can contribute with their experiences and knowledge.
Answer:
B. Core Competency
Explanation:
These factors are Amazon's core competencies, or main strengths that help differentiate Amazon from its competitors.
Finishing this job could cost as low as $222,000 in total. If the project is finished in 45 weeks, the final cost will be $400,000. If the project is completed in 46 weeks, the overall cost will be $405,000. The project is finished in 45 weeks, which has the lowest overall cost.
This project can be finished for as little as $222,000 overall. This is so that there is no penalty if the project is finished in 45 weeks. A $5,000 fine is imposed if the project is finished in less than 46 weeks. Thus, completing the project in 45 weeks results in the lowest overall cost. Examining the costs associated with each action is one method to approach this. The first activity will cost $40,000 to complete. The second activity will cost $60,000 to complete. The third activity will set you back $80,000. The fourth action will set you back $100,000. The sixth activity will set you back $120,000. The project will cost $400,000 in total. The overall cost, if the project takes 45 weeks to complete, is $400,000. The whole expense is $405,000 if the project is finished in 46 weeks. Thus, completing the project in 45 weeks results in the lowest overall cost.
To know more about Cost, refer to this link:
brainly.com/question/20534030
#SPJ4