Answer:
Total unitary cost= $4,800
Explanation:
Giving the following information:
Actual units= 800
Total fixed costs= 1,000*800= 800,000
UNitary variable cost= $4,000
Units increase= 200
<u>On unitary bases, variable costs remain constant. On the contrary, fixed costs vary at a unitary level. Now, the same amount of costs is divided by a larger number of units.</u>
<u></u>
Unitary fixed overhead= 800,000/1,000= $800
Total unitary cost= 4,000 + 800= $4,800
Answer:
federal loans are provided by the government and private loans are provided by banks, credit unions, and other financial institutions.
Explanation:
Answer: government taxes on products or services entering a country that primarily serve to raise prices on imports.
Explanation:
Tariffs are known to be taxes which the government of a particular country charges on goods and services which are imported into the country from other countries. It is a form of trade protection which the government uses in protecting local companies. Thus, the government imposes taxes on imported goods in order to make the prices of the goods high so that citizens can buy local or domestic goods and as a result encourage domestic companies to produce more of the local goods.
Answer:
e. $153,156
Explanation:
From 9/1/14, he needs $50,000 every year for 4 years to fund the tuition fees. Therefore, present value of the amount needed at 9/1/14 using the Present value of annuity due formula
= 50,000 * {1+ (1/(1.05)^4) } / 0.05 * (1.05)
= $186,162
$186,162 is the amount needed after 4 years. Amount you need to invest today to have this amount in four years = $186,162/(1.05)^4 = $186,162/1.21550625 = $153,156.40
Answer:
It's c.
Explanation:
Program Evaluation and Review Technique (PERT) is a method used in program management. It analyzes the time required to complete each task in a project and so tries to determine the minimum time to complete a project. It was developed by the US Navy in 1957.
In PERT analysis:
- there are 3 time estimates for every activity: optimistic, pessimistic, and most likely
-
you have to find the Critical Path. The Critical Path is the longest path of scheduled activities that must be met in order to execute a project. It is important to know because any problems on the critical path can prevent a project from moving forward and be delayed. Therefore only critical activities can contribute to the project variance.