Answer:
11.46 I believe
Step-by-step explanation:
Answer:
-m^4n^4
--------------
108
Step-by-step explanation:
Answers:
Lower bound = 41.3
Upper bound = 41.5
===========================================================
Explanation:
49.15 is the smallest f can be while 49.24 is the largest it can be. Well technically we could have something like 49.2499 or 49.24999 and so on. We slowly approach 49.25 but never actually get there
So the variable f is between 49.15 and 49.25 inclusive of the first value but excluding the second value. We can write it as 
For similar reasoning, 
-----------------
If we wanted to subtract those variables and get the smallest result possible, then we need to pick values that are closest together. It might help to set up a number line.
This means we'd go for f = 49.15 and g = 7.85
The lower bound for f-g is f-g = 49.15-7.85 = 41.3
In contrast, the upper bound is when the two variables are spaced as far apart as possible. The upper bound is f-g = 49.25 - 7.75 = 41.5
Area = 1/2 bh
96 = 1/2 x b x 8 = 4b
b = 96/4 = 24 inches
Perimeter = 3b [since the other sides are equal to the base]
P = 3 x 24 = 72 inches.
Answer:
0.1151 = 11.51% probability of completing the project over 20 days.
Step-by-step explanation:
Normal Probability Distribution
Problems of normal distributions can be solved using the z-score formula.
In a set with mean
and standard deviation
, the z-score of a measure X is given by:
The Z-score measures how many standard deviations the measure is from the mean. After finding the Z-score, we look at the z-score table and find the p-value associated with this z-score. This p-value is the probability that the value of the measure is smaller than X, that is, the percentile of X. Subtracting 1 by the p-value, we get the probability that the value of the measure is greater than X.
Expected completion time of the project = 22 days.
Variance of project completion time = 2.77
This means that 
What is the probability of completing the project over 20 days?
This is the p-value of Z when X = 20, so:



has a p-value of 0.1151.
0.1151 = 11.51% probability of completing the project over 20 days.