There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2. what is the probability tha
t the project will be completed in 38 weeks if its expected completion time is 40 weeks?
1 answer:
The expected completion time is μ = 40 weeks.
The random variable, X = 38 weeks (the probable time)
If the standard deviation is σ, then the z-score is z = (x - μ)/σ.
Let us test the given standard deviations.
When σ=1,
z = (38-40)/1 = -2
From standard tables,
P(x<=38) = P(z<=-2) = 0.0228 =2.3%
When σ=2,
z = (38*40)/2 = -1
P(x<=38) = P(z<=-1) = 0.1587 = 15.9%
When σ=4,
z = (38-40)/4 = -0.5
P(x<=38) = P(z<=-0.5) = 0.3085 = 30.9%
Answers:
z=1 => 2.3%
z=2 => 16% (approx)
z=4 => 31% (approx)
You might be interested in
Answer:
$522.49
Step-by-step explanation: 549.99*.05=27.50 (discount)
549.99-27.50=$522.49
Side a is 13 when using the pythagorean theorem
a^2 + b^2 = c^2
5^2 + 12^2 = c^2
25 + 144 = c^2
c^2 = 169
c = 13
Answer:
0.344
Step-by-step explanation:
i cant show reasoning its just 1.6 times 0.215
11% of 80 is 0.11*80=8.8
80-8.8=71.2
Answer B
Answer:
6.99 rounded up to 7 :))
Step-by-step explanation:
1/3 = 0.33
2.33 * 3 = 6.99 ft