There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2. what is the probability tha
t the project will be completed in 38 weeks if its expected completion time is 40 weeks?
1 answer:
The expected completion time is μ = 40 weeks.
The random variable, X = 38 weeks (the probable time)
If the standard deviation is σ, then the z-score is z = (x - μ)/σ.
Let us test the given standard deviations.
When σ=1,
z = (38-40)/1 = -2
From standard tables,
P(x<=38) = P(z<=-2) = 0.0228 =2.3%
When σ=2,
z = (38*40)/2 = -1
P(x<=38) = P(z<=-1) = 0.1587 = 15.9%
When σ=4,
z = (38-40)/4 = -0.5
P(x<=38) = P(z<=-0.5) = 0.3085 = 30.9%
Answers:
z=1 => 2.3%
z=2 => 16% (approx)
z=4 => 31% (approx)
You might be interested in
Answer: 25x^2 - 1^2
Explanation:
(5x+1) (5x-1)
(5x)^2 - 1^2
25x^2 - 1^2
Is this what you mean this is what i understood.
X-4=10;4x+1=57
First equation solve for x.
X-4=10
Add 4 both sides
X=10+4
X=14
Second equation substitute your x answer into second equation to make both sides equal.
4x+1=57
4(14)+1=57
56+1=57
57=57
Im actually pretty sure its C because 4 to the power of 2 is 16 and then add those too up 16+25=41
Your answer would be c. 18,6
The scale factor applied to the model is 8000. 8000 times one equals 8000