Answer:
6
Step-by-step explanation:
Answer:
15
Step-by-step explanation:
PERT estimate is a measuring strategy that is based on a weighted average. It is used in measuring the uncertainty and risk via three estimates to determine an estimated likelihood for a project's cost or period of completion.
The formula is (O + 4M + P) ÷ 6
Where P is the most pessimistic = 29
M is the most likely = 12
O is the most optimistic = 10
Hence we have (10 + [4*12]+ 29) ÷ 6
= (10 + 48 + 29) ÷ 6
= 87÷6 = 14.5 ≈ 15
Rounded figure is equal to 15.
Hence the final answer to the question is 15
You mean 28 divided by 7 bc thats 4 and for the other thing that is not the correct thing and it could never be true soooo.
Answer:
x=12
Step-by-step explanation:
2x-15 + 2x-6 = 15
4x = 36
x = 9
2 x 9 - 6 = 12