Answer: The response options are wrong, those that correspond according to what I found on the internet are:
All of the following are necessary to calculate the total purchase price for a Municipal bond traded on a yield basis in the secondary market EXCEPT:
A. Coupon rate
B. Yield to Maturity
C. Dated date
D. Trade date
<u>The correct answer is "C. Dated date".</u>
<u>Option "C" is correct because to calculate the price of a bond it is not necessary the day of issuance of the bond, is enough with its YIELD TO MATURITY, RATE CUPON AND YEARS TO MATURITY.</u>
Answer:
IRR is 18.25%
Annual amount is -$0.225 which closest to zero dollar,because at irr the investment return is zero
Explanation:
The formula for IRR in excel is :irr(values)
The formula can be applied to the cash outflow of $4,000 and cash inflow of $9,250 in five years' time as follows
Years Cash flow
0 -$4,000
1 $0
2 $0
3 $0
4 $0
5 $9,250
irr(-$4000 to $9,250)
irr is 18.25%
The amount of receivable each year can be computed using pmt formula in excel
=pmt(rate,nper,-pv,fv)
rate is the irr of 18.25%
pv is -$4000
fv is the future amount 0f $9,250
=pmt(18.25%,5,-4000,9250)
pmt=-$0.225 which closest to zero amount
Answer:
E) $3.00.
Explanation:
The computation of direct materials cost per equivalent unit is shown below:-
Equiavent unit with respect to material = $31,000 + $88,000 + $30,000
= 149000 units
Total direct material cost = $109,600 + $336,800
= $446,400
Direct materials cost per equivalent unit = Total direct material cost ÷ Equiavent unit with respect to material
= $446,400 ÷ 149,000
= $3 per unit
So, we have applied the above formula.
Answer:
The dealer will sell 15 Volvos
Explanation:
Consider the following formulas to calculate the Q of which optimize the exercise.
Profit = Q*p
Profit = (30-q)*q
Profit = 30q - q^2
Differentiating with respect to q, we get
30-2q = 0
2q = 30
q=15
The dealer will sell 15 Volvos
Answer:
During the initiation phase, what does project selection help to do?
The initiation phase entails the starting point of the project, project selection comes in after the scope, objectives and how it would be delivered has been defined thoroughly. Project selection helps to make decision to know when the project would be ready for delivery, also the format of execution would be known, furthermore, any deviation from the initiation would be detected early and corrected if there is any
Explanation: