Answer:
The correct answer is option (a).
Explanation:
According to the scenario, the given data are as follows:
Purchase Bonds = 60
Purchased bonds value = $60,000
So Purchased value of 30 bonds = $60,000 ÷ 2 = $30,000
Sold 30 bonds at value = $32,000
So, we can calculate the gain on sale by using following formula:
Gain on sale = Sold 30 bonds at value - Purchased value of 30 bonds
By putting the value, we get
= $32,000 - $30,000
= $2,000
Unemployment continues to rise to unacceptable level. As David Lipton said if the government are to navigate this dangerous period. Government must respond concretely to all of these challenges. Despite of political obstacles. This is important to all countries specially South Africa.
The capital projects fund account for the 10 percent retainage as (B) II only.
<h3>
What is retainage?</h3>
- Retainage is a percentage of the agreed-upon contract price withheld until the work is substantially completed to ensure that the contractor or subcontractor will fulfill its responsibilities and complete a construction project.
- Retention is money kept back by one party in a contract as security for unfinished or defective work.
- Assume the contract is worth $20,000 and you're submitting a paid app after finishing 25% of the work.
- So you earned $5,000 during the pay period, but retainage is 5%. The current progress payment has been reduced by $250.
- As a result, the "Amount Due for this Request" will be $4,750.
So, in the given situation the capital projects fund account for the 10 percent retainage as (II) the credit for $400,000 to Contracts Payable-Retained Percentage, that is (B) II only.
Therefore, the capital projects fund account for the 10 percent retainage as (B) II only.
Know more about retainage here:
brainly.com/question/24101126
#SPJ4
The correct question is given below:
The capital projects fund of Hood River completed the construction of an addition to its city hall at a cost of $4,000,000. The city council approved payment of the amount due to the general contractor, less a 10 percent retainage. How should the capital projects fund account for the 10 percent retainage?
I. As a credit of $400,000 to Deferred Revenue-Retained Percentage
II. As the credit for $400,000 to Contracts Payable-Retained Percentage.
A. I only
B. II only
C. Either I or II
D. Neither I nor II
Answer and Explanation:
a. The preparation of income statement is shown below:-
Income Statement
Service revenue $80,000
operating expenses
Salary expenses $28,000
Uncollectible accounts
expense $3,273
Total operating expense $31,273
Net income $48,727
Working Note :-
Days Amount Percentage Allowance balance
Current $16,800 0.01 $168
0-30 $5,100 0.05 $255
31-60 $4,000 0.10 $400
61-90 $2,000 0.30 $600
Over 90
days $3,700 0.50 $1,850
Total $31,600 $3,273
b. The computation of net realizable value of the accounts receivable is shown below:-
Net realizable value = Accounts receivable - Allowance for doubtful accounts
= ($80,000 - $48,400) - $3,273
= $31,600 - $3,273
= $28,327