Answer: project manager
Explanation: The project manager's role. A project manager is a person who is responsible for initiating, preparing, designing, implementing, tracking, overseeing and closing a project successfully. A project manager is a person in charge for both smaller and larger decision-making.
Hence, as he or she is responsible for successful completion it is the responsibility of the project manager to define, approve and acquire all the documentation needed regarding the project.
Answer:
Gain recognized by Tom is $10000
So option (b) will be correct answer
Explanation :
We have given liability on bulding assumed by Paul Corp = $30,000
Tom's adjusted basis in the building = $20,000
Since the liability assumed by Paul Corp on the building is greater than Tom's adjusted basis, Tom must recognize gain equal to the difference between the liability on the building and his adjusted basis.
So gain recognized by Tom = $30,000 - $20,000 = $10,000
Answer:
Its action would be optimal given an ordering cost of $28.31 per order
Explanation:
According to the given data we have the following:
economic order quantity, EOQ= 55 units
annual demand, D=235
holding cost per one unit per year, H=40%×$11=$4.4
ordering cost, S=?
In order to calculate the ordering cost we would have to use the following formula:
EOQ=√(<u>2×D×S)</u>
(H)
Hence, S=<u>(EOQ)∧2×H</u>
2×D
S=<u>(55)∧2×4.4</u>
2×235
S=<u>13,310</u>
470
S=$28.31
Its action would be optimal given an ordering cost of $28.31 per order
1.Technical Certified/VRQ (Vocational related Qualification)
2.NVQ (National Vocational Qualification)
3.Key skills
4.EER (Employment Rights & Responsibilities)
Answer:
The correct answer is: scope.
Explanation:
Earned Value Management (<em>EVM</em>) is a helpful method that allows high-rank executives to measure the performance of their projects. It analyses the difference between the work planned in the project with the work performed. The three pillars of EVM are <em>scope, time, </em>and <em>cost information</em>. The scoping process implies a Work Breakdown Structure (<em>WBS</em>) where the initial plan is broken into micro levels for better analysis.