Answer:
= Available for Work, Seeking for Work, Currently not Working
Answer:
none of these terms are like terms
Answer:
a. The percentage of vehicles who pass through this construction zone who are exceeding the posted speed limit =90.82%
b. Percentage of vehicles travel through this construction zone with speeds between 50 mph and 55 mph= 2.28%
Step-by-step explanation:
We have to find
a) P(X>40)= 1- P(x=40)
Using the z statistic
Here
x= 40 mph
u= 44mph
σ= 3 mph
z=(40-44)/3=-1.33
From the z-table -1.67 = 0.9082
a) P(X>40)=
Probability exceeding the speed limit = 0.9082 = 90.82%
b) P(50<X<55)
Now
z1 = (50-44)/3 = 2
z2 = (55-44)/3= 3.67
Area for z>3.59 is almost equal to 1
From the z- table we get
P(55 < X < 60) = P((50-44)/3 < z < (55-44)/3)
= P(2 < z < 3.67)
= P(z<3.67) - P(z<2)
= 1 - 0.9772
= 0.0228
or 2.28%
"The intersection (∩) of a pair of sets (G and H) is a third set (I) composed by the elements that belong, at the same time, to both given sets."
According to this definition:
Given the sets:
G = {3, 7, 8, 9}
H = {2, 5, 7, 8}
The Intersection is:
G ∩ H = I = {7, 8}
:-)
You want to find the monthly average over the past 6 months.
July: $78.56
August: $30.21
September: $81.20
October: $79.08
November: $66.18
December: $100.75
Add all of these up
(July) $78.56
(August) $30.21
(September) $81.20
(October) $79.08
(November) $66.18
(December) + $100.75
----------------------------------------------
(Total cost) $435.88
There are 6 months you are calculating for, therefore divide the total (combined) cost of 6 months with the total number of months (in this case, 6)
$435.88 (total cost of 6 months) ÷ 6 (months)
The average cost per month of over the past 6 months is $72.66.