Answer:
Instructions are below.
Explanation:
Giving the following information:
Variable cost:
Direct material= $0.50 per unit
Fixed cost:
Fixed overhead= $15,000
Total cost for 10,000 units:
Variable cost= 0.50*10,000= 5,000
Fixed costs= 15,000
Total cost= $20,000
Total cost for 15,000 units:
Variable cost= 0.50*15,000= 7,500
Fixed costs= 15,000
Total cost= $22,500
Answer:
Standard deviation = 47.69% (Approx)
Explanation:
Given:
Portfolio of Apple stock w1 = 25% = 0.25
Portfolio of Tesla stock w2 = 75% = 0.75
Standard deviation return Apple σ1 = 35% = 0.35
Standard deviation return Tesla σ2 = 60% = 0.60
Correlation coefficient ρ12 = 0.22
Find:
Standard deviation
Computation:
Standard deviation = √w1²σ1² + w2²σ2² + 2w1σ1w2σ2ρ12
Standard deviation = 0.4769
Standard deviation = 47.69% (Approx)
Answer:
Neither project should be chosen
Explanation:
Given that
Each project cost of capital is 12%
The IRR of project A is 11.4%
And, the IRR of project B is 11.1%
As we can see that the cost of capital of each project with their internal rate of return so no project should be selected
Therefore the above statement represent an answer
The same should be relevant
Answer:
Instructions are below.
Explanation:
Giving the following information:
Sales:
April 45,000
May 38,000
June 42,000
Each unit requires one pound of raw material. Saphire's policy is to have 30% of the following month's production needs for materials in inventory.
A) Budgeted production= sales + desired ending inventory - beginning inventory
Budgeted production:
Sales=38,000
Ending inventory= 42,000*0.3= 12,600
Beginning inventory= 38,000*0.3= (11,400)
Total= 39,200
B) Desired beginning inventory= budgeted sales*30%
Beginning inventory= 42,000*0.3= 12,600
Answer: 11%
Explanation:
Arithemetic mean is the average of a set of numeric variables that is calculated by adding them up and dividing by the number of variables there are.
= (0.17 + (-0.04) + 0.2 + 0.12 + 0.10)/5
= 0.55/5
= 0.11
= 11%