Answer:
Our answer is 2430798.798
Explanation:
. 70% of pre-retirement salary should be equal to the interest that we get from savings(5% of savings).
Therefore, 0.7 × 173628.4856 = 0.05×savings
==> savings = 2430798.798
Answer:
Explanation:
Date Unit Unit cost Total Goods sold Cost Total
May 1 28 9 252 28 9 252
May 15 26 10 260 26 10 260
May 24 39 11 429 26 11 286
Total 93 941 80
1) Weighted average unit cost = 941/93 = $10.118
FIFO method
2)Ending inventory (93-80)*11 =$ 143
FIFO method assumes that the first set of inventory are the first to be sold
LIFO method
LIFO assumes that the last set of inventory are the first to be sold
Goods Sold Cost Total
39 11 429
26 10 260
15 9 135
Ending Inventory = (93-80)*9 = $117
Average Cost Method
Ending Inventory = 13 * 10.118 =$131.534
Answer:
8.32%
Explanation:
The computation of cost reduction improve the ROE is shown below:-
For computing the increase in ROE first we need to follow some steps which is here below:-
Debt = capital × Debt
= $250,000 × 37.5%
= $93,750
Equity = Assets - Debt
= $250,000 - $93,750
= $156,250
New ROE = New Net income ÷ Equity
= $33,000 ÷ $156,250
= 21.12%
Old ROE = Old Net income ÷ Equity
= $20,000 ÷ $156,250
= 12.8%
Increase in ROE = New ROE- Old ROE
= 21.12% - 12.8%
= 8.32%
Answer: $789855
Explanation:
Initial liability = $1,006,192
Less: Payment = $159,000
Liability = $847192
× Implicit rate 12%
Interest = 12% × $847192 = $101663
Then, reduced balance will be:
= Payment - Interest
= $159,000 - $101663
= $57337
Therefore, Francisco lease liability at December 31, 2022 will be:
= $847192 - $57337
= $789855
Answer:
The cost assigned to Job 7 at the end of the week is 5,700 dollars.
Explanation:
In job order costing the cost that is to be assign to a specific order is sum of actual direct material cost and actual labour cost require to perform that job. Factory overheads are also added to the job cost on the basis of allocation method (on basis of budgeted applied OH rate).
So Following costs will be assign to Job 7.
RAW materail = $ 700
Labor Cost = $ 3000
Overhead = $ 2000 (10* 20)
Total Cost = $ 5700