Answer:
A,B, and C
Step-by-step explanation:
All of the answers are correct besides D, none of the above
The diagonals bisect each other
Answer:
Project A :
NPV : $703,888.64
IRR : 44.882%
Project B:
NPV : $5,241.26
IRR : 49.662%
Project B is more profitable
Step-by-step explanation:
The NPV gives the difference between the present value of cash inflow and cash outflow over a certain period of time.
The Internal rate of return is the discount rate which makes the NPV of an investment 0. It is used to estimate the potential return on an investment. Investments with higher IRR are said to be better than those with lower IRR value.
Using the net present value, (NPV) Calculator, the NPV for project A is : $703,888.64
The IRR of project A is : 44.882%
The NPV for Project B is : $5,241.26
The Internal rate of return (IRR) : 49.662%
From the Internal rate of return value obtained, we can conclude that, project B is more profitable as it has a higher IRR than project A.
Answer:
32 in²
Step-by-step explanation:
A= ((a+b)/2)*h
A= ((6+10)/2)*4
A=32
The given equations are

(1)

(2)
When t=0, obtain

Obtain derivatives of (1) and find x'(0).
x' (t+1) + x - 4√x - 4t*[(1/2)*1/√x = 0
x' (t+1) + x - 4√x -27/√x = 0
When t=0, obtain
x'(0) + x(0) - 4√x(0) = 0
x'(0) + 9 - 4*3 = 0
x'(0) = 3
Here, x' means

.
Obtain the derivative of (2) and find y'(0).
2y' + 4*(3/2)*(√y)*(y') = 3t² + 1
When t=0, obtain
2y'(0) +6√y(0) * y'(0) = 1
2y'(0) = 1
y'(0) = 1/2.
Here, y' means

.
Because

, obtain

Answer:
The slope of the curve at t=0 is 1/6.