Answer:
recovery
Explanation:
There is one framework for each of the five mission areas wich are Prevention,protection, mitigation,response, and Recovery
Hope this helped you!
The purpose of verification, as a normal motion, is to become aware of the faults/defects introduced at the time of any transformation of inputs into outputs.
Verification is a pleasant manage technique that determines if a machine meets its gadget-stage necessities. Inspection and demonstration is the principle testing technique used in Verification.
The Verification procedure offers the evidence that the gadget or machine detail plays its meant capabilities and meets all performance requirements listed inside the machine overall performance specification and functional and allotted baselines.
Learn more about verification method here:brainly.com/question/14513832
#SPJ4
Answer:
Cost of land = $1,005,000
Cost of building = $4,275,000
Explanation:
The calculation of cost of the land and new building is shown below:-
Cost of land = Purchase cost + Demolition of old building + Legal fees for title investigation and purchase contract - Salvaged materials
= $960,000 + $ 60,000 + 15,000 - $30,000
= $1,005,000
Cost of building = Architects Fees + Construction costs
= $105,000 + $4,170,000
= $4,275,000
Answer:
It will incur an Opportunity cost of $8,000.
Explanation:
It will incur the opportunity cost of $8000 because the additional unit produces by the company then the additional revenue that is generated will be equal to the amount (25 - 20) x 12,000 = 60,000. Since the additional cost, that incurs for the production of 12000 units is 52000. Therefore the profit earned is $8000.
So if the company does not produce it then it will lose the profit of $8000.