5

A roller conveyor moves tote pans at 200 ft/min between a load station and an unload station, a distance of 250 ft. The time to

load parts into a tote pan at the load station is 0.05 min/part. Each tote pan holds 12 parts. In addition, it takes 0.15 min to load a tote pan onto the conveyor. One worker is assigned to loading the parts and then loading the tote pan onto the conveyor. Determine (a) the spacing between tote pan centers flowing in the conveyor system, and (b) the flow rate of parts on the conveyor system. (c) Consider the effect of the unit load principle. Suppose the tote pans were smaller and could hold only one part rather than 12. Determine the flow rate in this case if it takes 0.10 min to load a tote pan onto the conveyor (instead of 0.15 min for
Engineering
1 answer:
Serjik [45]3 years ago
4 0

Answer:

A.) The spacing between tote pan centers flowing in the conveyor system is 150ft/tote

B.)

Explanation:

Zbxbxbbdbjxjdd

You might be interested in
How can the direction of rotation of a split-phase motor be changed? *
S_A_V [24]

Nejejenshsjsjsjs:

Explanation:rjejsjjejej

8 0
3 years ago
Read 2 more answers
Select the right answer<br>​
Kruka [31]

Answer:

for 1st question the answer is 5th option.

for 2nd question the answer is 2nd option

hope it helps you mate

please mark me as brainliast

5 0
4 years ago
Build a 32-bit accumulator circuit. The circuit features a control signal inc and enable input en. If en is 1 and inc is 1, the
Alex_Xolod [135]

Sorry need.points I'm new

7 0
4 years ago
Let A→=(150iˆ+270jˆ) mm , B→=(300iˆ−450jˆ) mm , and C→=(−100iˆ−250jˆ) mm . Find scalars r and s, if possible, such that R→=rA→+s
ioda

Answer: r = 0.8081; s = -0.07071

Explanation:

A = (150i + 270j) mm

B = (300i - 450j) mm

C = (-100i - 250j) mm

R = rA + sB + C = 0i + 0j

R = r(150i + 270j) + s(300i - 450j) + (-100i - 250j) = 0i + 0j

R = (150r + 300s - 100)i + (270r - 450s - 250)j = 0i + 0j

Equating the i and j components;

150r + 300s - 100 = 0

270r - 450s - 250 = 0

150r + 300s = 100

270r - 450s = 250

solving simultaneously,

r = 0.8081 and s = -0.07071

QED!

5 0
4 years ago
Three tool materials (high-speed steel, cemented carbide, and ceramic) are to be compared for the same turning operation on a ba
Tpy6a [65]

Answer:

Among all three tools, the ceramic tool is taking the least time for the production of a batch, however, machining from the HSS tool is taking the highest time.

Explanation:

The optimum cutting speed for the minimum cost

V_{opt}= \frac{C}{\left[\left(T_c+\frac{C_e}{C_m}\right)\left(\frac{1}{n}-1\right)\right]^n}\;\cdots(i)

Where,

C,n = Taylor equation parameters

T_h =Tool changing time in minutes

C_e=Cost per grinding per edge

C_m= Machine and operator cost per minute

On comparing with the Taylor equation VT^n=C,

Tool life,

T= \left[ \left(T_t+\frac{C_e}{C_m}\right)\left(\frac{1}{n}-1\right)\right]}\;\cdots(ii)

Given that,  

Cost of operator and machine time=\$40/hr=\$0.667/min

Batch setting time = 2 hr

Part handling time: T_h=2.5 min

Part diameter: D=73 mm =73\times 10^{-3} m

Part length: l=250 mm=250\times 10^{-3} m

Feed: f=0.30 mm/rev= 0.3\times 10^{-3} m/rev

Depth of cut: d=3.5 mm

For the HSS tool:

Tool cost is $20 and it can be ground and reground 15 times and the grinding= $2/grind.

So, C_e= \$20/15+2=\$3.33/edge

Tool changing time, T_t=3 min.

C= 80 m/min

n=0.130

(a) From equation (i), cutting speed for the minimum cost:

V_{opt}= \frac {80}{\left[ \left(3+\frac{3.33}{0.667}\right)\left(\frac{1}{0.13}-1\right)\right]^{0.13}}

\Rightarrow 47.7 m/min

(b) From equation (ii), the tool life,

T=\left(3+\frac{3.33}{0.667}\right)\left(\frac{1}{0.13}-1\right)\right]}

\Rightarrow T=53.4 min

(c) Cycle time: T_c=T_h+T_m+\frac{T_t}{n_p}

where,

T_m= Machining time for one part

n_p= Number of pieces cut in one tool life

T_m= \frac{l}{fN} min, where N=\frac{V_{opt}}{\pi D} is the rpm of the spindle.

\Rightarrow T_m= \frac{\pi D l}{fV_{opt}}

\Rightarrow T_m=\frac{\pi \times 73 \times 250\times 10^{-6}}{0.3\times 10^{-3}\times 47.7}=4.01 min/pc

So, the number of parts produced in one tool life

n_p=\frac {T}{T_m}

\Rightarrow n_p=\frac {53.4}{4.01}=13.3

Round it to the lower integer

\Rightarrow n_p=13

So, the cycle time

T_c=2.5+4.01+\frac{3}{13}=6.74 min/pc

(d) Cost per production unit:

C_c= C_mT_c+\frac{C_e}{n_p}

\Rightarrow C_c=0.667\times6.74+\frac{3.33}{13}=\$4.75/pc

(e) Total time to complete the batch= Sum of setup time and production time for one batch

=2\times60+ {50\times 6.74}{50}=457 min=7.62 hr.

(f) The proportion of time spent actually cutting metal

=\frac{50\times4.01}{457}=0.4387=43.87\%

Now, for the cemented carbide tool:

Cost per edge,

C_e= \$8/6=\$1.33/edge

Tool changing time, T_t=1min

C= 650 m/min

n=0.30

(a) Cutting speed for the minimum cost:

V_{opt}= \frac {650}{\left[ \left(1+\frac{1.33}{0.667}\right)\left(\frac{1}{0.3}-1\right)\right]^{0.3}}=363m/min [from(i)]

(b) Tool life,

T=\left[ \left(1+\frac{1.33}{0.667}\right)\left(\frac{1}{0.3}-1\right)\right]=7min [from(ii)]

(c) Cycle time:

T_c=T_h+T_m+\frac{T_t}{n_p}

T_m= \frac{\pi D l}{fV_{opt}}

\Rightarrow T_m=\frac{\pi \times 73 \times 250\times 10^{-6}}{0.3\times 10^{-3}\times 363}=0.53min/pc

n_p=\frac {7}{0.53}=13.2

\Rightarrow n_p=13 [ nearest lower integer]

So, the cycle time

T_c=2.5+0.53+\frac{1}{13}=3.11 min/pc

(d) Cost per production unit:

C_c= C_mT_c+\frac{C_e}{n_p}

\Rightarrow C_c=0.667\times3.11+\frac{1.33}{13}=\$2.18/pc

(e) Total time to complete the batch=2\times60+ {50\times 3.11}{50}=275.5 min=4.59 hr.

(f) The proportion of time spent actually cutting metal

=\frac{50\times0.53}{275.5}=0.0962=9.62\%

Similarly, for the ceramic tool:

C_e= \$10/6=\$1.67/edge

T_t-1min

C= 3500 m/min

n=0.6

(a) Cutting speed:

V_{opt}= \frac {3500}{\left[ \left(1+\frac{1.67}{0.667}\right)\left(\frac{1}{0.6}-1\right)\right]^{0.6}}

\Rightarrow V_{opt}=2105 m/min

(b) Tool life,

T=\left[ \left(1+\frac{1.67}{0.667}\right)\left(\frac{1}{0.6}-1\right)\right]=2.33 min

(c) Cycle time:

T_c=T_h+T_m+\frac{T_t}{n_p}

\Rightarrow T_m=\frac{\pi \times 73 \times 250\times 10^{-6}}{0.3\times 10^{-3}\times 2105}=0.091 min/pc

n_p=\frac {2.33}{0.091}=25.6

\Rightarrow n_p=25 pc/tool\; life

So,

T_c=2.5+0.091+\frac{1}{25}=2.63 min/pc

(d) Cost per production unit:

C_c= C_mT_c+\frac{C_e}{n_p}

\Rightarrow C_c=0.667\times2.63+\frac{1.67}{25}=$1.82/pc

(e) Total time to complete the batch

=2\times60+ {50\times 2.63}=251.5 min=4.19 hr.

(f) The proportion of time spent actually cutting metal

=\frac{50\times0.091}{251.5}=0.0181=1.81\%

3 0
4 years ago
Other questions:
  • Practicing new things strains your brain fibers, weakening your ability to make connections.
    13·1 answer
  • Tadpoles raised in water with atrazine levels of 0.1 ppb should produce a higher percentage of male frogs with gonadal abnormali
    13·1 answer
  • What must engineers keep in mind so that their solutions will be appropriate? O abstract knowledge O context O scientists persev
    12·1 answer
  • In very early human history, complex sanitation systems were not needed because settlements were usually very small, like the vi
    10·2 answers
  • Sketch the velocity profile for laminar and turbulent flow.
    15·1 answer
  • B1) 20 pts. The thickness of each of the two sheets to be resistance spot welded is 3.5 mm. It is desired to form a weld nugget
    12·1 answer
  • The equation for the velocity V in a pipe with diameter d and length L, under laminar condition is given by the equation V=Δpdsq
    10·1 answer
  • I need solution fast plesss​
    9·1 answer
  • Air is compressed by a 30-kW compressor from P1 to P2. The air temperature is maintained constant at 25°C during this process as
    11·1 answer
  • Describe how to mix and apply body filler?
    13·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!