Answer:
the first one
Step-by-step explanation:
A graph showing the Earliest Start Times (EST) for project tasks is computed left to right based on the predecessor task durations. For dependent tasks, the earliest start time will be the latest of the finish times of predecessor tasks.
The first graph appears to appropriately represent the table values, using edges to represent task duration, and bubble numbers to represent start times.
The second graph does not appropriately account for duration of predecessor tasks.
The third graph seems to incorrectly compute task completion times (even if you assume that the edge/bubble number swap is acceptable).
7. 0.78 8. 0.55 9. 0.185 10. 0.574 11. 0.33 12. 0.09 13. 0.4763 14. 0.9125
15. 1.66 16. 2.17 17. 0.0006 18. 0.00034 19. 74% 20. 52% 21. 89% 22. 76.8%
23. 99% 24. 49% 25. 48.7% 26. 12.8% 27. 368% 28. 512% 29. 3.71%
30. 0.46% Converting Decimal to Percentage, Multiply Decimal by 100. Percentage to Decimal, divide by 100.
The number of kids in your group is 12.
Step-by-step explanation:
Given,
Number of people = 20
Cost of each kid ticket = $4
Cost of each adult ticket = $6
Total spent = $96
Let,
x be the number of kids ticket
y be the number of adult ticket
According to given statement;
x+y=20 Eqn 1
4x+6y=96 Eqn 2
Multiplying Eqn 1 by 4

Subtracting Eqn 3 from Eqn 2

Dividing both sides by 2

Putting y=8 in Eqn 1

The number of kids in your group is 12.
Keywords: linear equation, elimination method
Learn more about elimination method at:
#LearnwithBrainly
Answer:
-17-17,-17,-17,-14,-14,-14,-14,6,6,6,6
Step-by-step explanation:
hope it helped.