Answer:
The following statement is True.
Explanation:
Because when we are applying the pair t-test then, take differences of that pair and then treat it as an individual samples. Formula for the test is a statistic and in this case, it is also same as formula in the one-sample of t statistics.
Therefore, it will be an equivalent to the one-sample t-test.
A macro is that pseudo-program that performs a list of actions based on a set of instructions.
<h3>What is macro?</h3>
A macro can be said to be a number of commands that help you to get complex things done via automating simple and via repetitive tasks.
A macro is that pseudo-program that performs a list of actions based on a set of instructions.
Therefore, option A is correct as the macros does a whole lot of work.
Learn more about macro from
brainly.com/question/20050035
#SPJ1
Answer:
I think thats just a software issue. i have the same problem
Explanation:
Answer:
There are multiple critical paths
Explanation:
The critical path method (CPM), or critical path analysis (CPA), is an algorithm for scheduling a set of project activities. It is commonly used in conjunction with the program evaluation and review technique (PERT). A critical path is determined by identifying the longest stretch of dependent activities and measuring the time required to complete them from start to finish.
The essential technique for using CPM is to construct a model of the project that includes the following:
- A list of all activities required to complete the project (typically categorized within a work breakdown structure),
- The time (duration) that each activity will take to complete,
- The dependencies between the activities and,
- Logical end points such as milestones or deliverable items.
Using these values, CPM calculates the longest path of planned activities to logical end points or to the end of the project, and the earliest and latest that each activity can start and finish without making the project longer. This process determines which activities are "critical" (i.e., on the longest path) and which have "total float" (i.e., can be delayed without making the project longer).
considering the above function of the cpm analysis because you have multiple path, there is tendency that more than path through the project network will have zero slack values.