Answer:
Material Cost variance = Standard cost - Actual cost
= 3000*5 - 16192
= 1192 A
Material Rate Variance = (S.R. - A.R.)A.Q
= (5 - 5.06)3200
= 192 A
Material usage variance = (S.Q. - A.Q.)S.R
= (3000 - 3200)5
= 1000 A
Working Notes:
Actual Output = 1500 units
Standard qty of Material for Actual Output = 1500*2
= 3000 pounds
Actual qty. used = 3200 pounds
Actual rate/pound = $16192/3200
= $5.06
Answer:
Expected rate of return is 13%
Explanation:
Using the expected values method:
Expected Rate of return = Chance 1 * Outcome 1 + Chance 2 * Outcome 2 + Chance 3 * Outcome 3 + ................... Chance n * Outcome n
So by putting values, we have:
Expected Rate of return = 30% * 20% + 30% * 10% + 40% * 10%
Expected Rate of return = 6% + 3% + 4% = 13%
So the expected rate of return using the expected value method is 13%
Answer: Option B
Explanation: Economic efficiency refers to a situation when all the resources that exist in an economy are allocated in such a way that all the individuals and entities in the economy is getting the maximum utility out of them.
In an efficient economy the surplus of both consumer and supplier are maximum and any increase or decrease in resource allocation will only result in harm of the economy.
Hence from the above we can conclude that the correct option is B.
Answer:
Superintendent, Principal, teacher, student
Explanation:
Answer: The answers are provided below
Explanation:
There are several similarities between the project management processes which surround scrum to the traditional project management processes which surrounds a project life cycle such as Waterfall. When one looks at each iteration as a project, one will see that Scrum planning meeting will be identical to planning meeting of the traditional project.
The daily standups in scrum will resemble the monitoring and the controlling of traditional waterfall with the exception that in scrum, its team monitors itself. A sprint would be the execution stage while the sprint review will be like project closure lessons that are learned. Sprint can be seen as small waterfall model project.
However, the main difference is in the scrum's team mindset versus the team of the traditional project management. Also, the process of work defining as being completed is different for the teams. Lastly, the method used by the scrum team in its approaches to work, team collaboration, responsibility acceptance, tasks definition and accountability are different from the traditional project management team.
A hybrid approach will be sensible in a large organization which has pockets of power. This is true for large retails that have old legacy systems in which frequent deployments aren't possible.
This is true for systems in which, testing can't be automated due to the fact that automated testing is a vital part for success for large scrum projects. In such organizations, it is sensible to use scrum for the teams which are able to move to scrum and waterfall can be used for other parts of the organization.