Answer:
.
Step-by-step explanation:
Answer:
5/6 (i think im not good at math soz)
-Mina
Step-by-step explanation:
Branily stop deleting my awnsers
Answer:
If ‘A’ can finish a work in ‘n’ days then part of work finished in 1 day
will be
.
Step-by-step explanation:
From the question, it is clear that
- If ‘A’ can finish a work in ‘n’ days, then
- we have to determine the part of work finished in 1 day.
So
let '
' be the number of days
takes to complete the whole work
Let the whole job be denoted as '
'
Thus, the part of work finished in 1 day will be:

Therefore, If ‘A’ can finish a work in ‘n’ days then part of work finished in 1 day will be
.
Keywords: work, word problem
Learn more about word problem form brainly.com/question/12419898
#learnwithBrainly
Answer:
41
Step-by-step explanation:
Step 1:
12x - 7 Equation
Step 2:
12 ( 4 ) - 7 Input x value
Step 3:
48 - 7 Multiply
Answer:
41 Subtract
Hope This Helps :)
Step-by-step explanation:
this is the right answer..hope it helped you .