Answer:
False
Explanation:
If an investment project can be repeated, i.e. its life cycle can be extended by reinvesting, the NPV of the project will change.
When considering two mutually exclusive projects, the NPV method should always be considered before the IRR as a means of evaluating which project should be carried out.
Answer:
Res ipsa loquitur
Explanation:
_____ is a tort in which the presumption of negligence arises because the defendant was in exclusive control of the situation, and the plaintiff would not have suffered injury but for someone's negligence.
Res ipsa loquitur is a doctrine in law that one can presume the negligence of a defendant when the facts are glaring.The doctrine has primarily required that a defendant have exclusive power over the occurrence of an injury. negligence could result from
1. an actual causal connection between the defendant's conduct and the resulting harm; 2 a duty of care owed by the defendant to the plaintiff; 3 a breach of that duty;
Answer:
a. Project’s IRR is 18.28%
b. Project should be accepted and pursued because it IRR is higher than the required rate of return.
Explanation:
Cash flows are missing a similar question is attached and followoing answer is made accordingly.
Year 0 1 2 3 NPV
Cash flows -$10,000 $0 $7,500 $8,500
PV @ 10% -$10,000 $0 $6,198 $6,386 = $2,584
PV @5% -$10,000 $0 $6,802 $7,342 = $4,144
IRR = 0.05 + ( 4,144 / (4,144-2,584)) x (0.1-0.05) = 18.28%
Answer:
Explanation:
1. Calculate the efficiency variance for variable overhead setup costs.
This will be calculated as:
= Standard Hours - Actual Hours) × Standard rate
= (15000/225 × 5.25 - 15000/250 × 5) × 38
= (350 - 300) × 38
= 50 × 38
= 1900 Favourable
2) Calculate the rate variance for variable overhead setup costs.
This will be:
= Standard rate- Actual rate) × Actual Hour
= (38-40) × (15000/250 × 5)
= -2 × 300
= -600 Unfavourable
3) Calculate the flexible-budget spending variance for variable overhead setup costs.
This will be the difference between the standard cost and the actual cost. This will be:
= (15000/225×5.25 ×38) - (15000/250×5 ×40)
= 13300 - 12000
= 1300 Favourable
4) Calculate the spending variance for fixed setup overhead costs.
what formular did you use.
This will be:
= Standard Cost - Actual Cost
= 9975-12000
= -2025 Unfavorable