Its T : 400
H : 20 Hope this help fam because 200 isn't the answer.
The polynomial is not factorable, so use the quadratic formula.
y^2 + 8y + 19 = 0
x = (-b +- sqrt(b^2 - 4ac))/(2a)
x = (-8 +- sqrt(8^2 - 4(1)(19))/(2 * 1)
x = (-8 +- sqrt(64 - 76))/2
x = (-8 +- sqrt(-12))/2
If you have not learned imaginary/complex numbers, then the answer is "No solution" since there is no real number solution.
If you have learned imaginary/complex numbers, then we'll continue.
x = (-8 +- 2i sqrt(3))/2
x = -4 +- i sqrt(3)
Answer:
D |-11 | >-25
Step-by-step explanation:
|-11 | = 11
11 > -25
Answer: the answer is 0.6
Step-by-step explanation:
you divide 3 by 5
Answer: 14 weeks 5 days
Step-by-step explanation:
From the question, we are informed that Amir has 103 days to finish a project and that he works 7 days a week on the project.
The number of weeks and days that he has to finish the project will be:
= 103/7
= 14 5/7
= 14 weeks 5 days