Answer:
Enthalpy at outlet=284.44 KJ
Explanation:


We need to Find enthalpy of outlet.
Lets take the outlet mass m and outlet enthalpy h.
So from mass conservation

m=1+1.5+2 Kg/s
m=4.5 Kg/s
Now from energy conservation

By putting the values

So h=284.44 KJ
Answer:
1. Loss of income.
2. Rental costs.
3. Utility bills.
4. Loss of rent.
5. Storage costs.
Explanation:
Liquidated damages can be defined as pre-determined damages or clauses that are highlighted or indicated at the time of entering into a contract between a contractor and a client which is mainly based on evaluation of the actual loss the client may incur should the contractor fail to meet the agreed completion date.
Generally, liquidated damages are meant to be fair rather than being a penalty or punitive to the defaulter. It is usually calculated on a daily basis for the loss.
When entering into a contract with another, liquidated damages are intended to represent anticipated losses to the owner based upon circumstances existing at the time the contract was made.
Listed below are five (5) types of potential losses to the owner that would qualify for determination of such potential losses;
1. Loss of income.
2. Rental costs.
3. Utility bills.
4. Loss of rent.
5. Storage costs.
Answer:
4.6398 kg/day
Explanation:
Please find attached file for complete answer solution.
Answer:

Explanation:
Given


Required
Determine the pressure
Pressure is calculated using:

Substitute values for Force and Area


Change units

Answer:
"Test Phase
" is the correct choice.
Explanation:
- DevSecOps seems to be a community as well as experience of corporate data science which encompasses software design, regulation, including operational activities. This same main feature of DevSecOps has always been to strengthen customer achievement as well as expedition importance by computerizing, supervising as well as implementing data protection at all stages of the development including its development tools.
- The testing method throughout the test phase would then help make sure that the controller is designed mostly under the responsibilities forecasted. The test focuses on either the reaction times, dependability, use of resources but instead interoperability of applications.